Project Manager for a new two story addition to the Butler Tech Bioscience Building in West Chester, OH.
Working as the Construction Manager on site for multiple phases of a school renovation. I am responsible for working with my Project Manager and alongside the Design Team and the Owner.
Responsibilities include:
Current Project:
- Renovation in phases of approximately 50,000sf of classrooms, kitchen, and cafeteria
- New construction of 18,000sf for new admin space, classrooms, and second cafeteria
Worked as on site Project Manager for several different projects on one high school campus. I am responsible for the financials of the projects along with my SR PM and Project Executive. Responsibilities include:
Projects include:
- Renovation of 150,000sf of classrooms, kitchen, cafeteria space over 9
phases. School remained in session during the entire duration.
- Complete demo of existing pool from roof all the way down to footers.
Installing new pool, super structure, and roof.
- Renovation of 1st and 2nd floor locker room area, as well as
renovation of existing gym.
- New concession stand, 3,500 seat football stadium, and parking lot
on the school grounds.
Worked as on site Project Engineer for several projects. Supported the Project Executive, SR PM, and Superintendent. Responsibilities included:
Projects include:
- 15,000sf addition for new Pre-K and Kindergarten classrooms. Full
renovation of the existing 62,000sf school along with sitework that
added parking.
- Full demo and renovation of 6 floors, totaling 33,000sf.
- Added a grand staircase in the middle that went from the first floor
all the way up to the 6th floor.