Justin Barth

Newport,KY

Overview

7
7
years of professional experience

Work History

Project Manager

Pepper Construction
09.2024 - Current

Project Manager for a new two story addition to the Butler Tech Bioscience Building in West Chester, OH.

  • It is a $12 million project that is currently in buyout phase.
  • I am responsible for buyout, writing subcontracts, and establishing the 14 month schedule to get us from procurement to commissioning.

Construction Manager

Codell Construction
11.2023 - 08.2024

Working as the Construction Manager on site for multiple phases of a school renovation. I am responsible for working with my Project Manager and alongside the Design Team and the Owner.

Responsibilities include:

  • Leading weekly contractor meetings.
  • Preparing change orders, RFI's, reviewing submittals.
  • Updating and maintaining schedule.

Current Project:

  • Ludlow Schools - Addition and Renovation - $32 million

- Renovation in phases of approximately 50,000sf of classrooms, kitchen, and cafeteria

- New construction of 18,000sf for new admin space, classrooms, and second cafeteria

Project Manager

HGC Construction
09.2021 - 11.2023

Worked as on site Project Manager for several different projects on one high school campus. I am responsible for the financials of the projects along with my SR PM and Project Executive. Responsibilities include:

  • Leading weekly OAC meetings.
  • Issuing LOI's, subcontracts, change orders, RFI's, submittals, updating and maintaining schedule.
  • Being the main point of contact for the owner and owners rep.

Projects include:

  • Sycamore HS - Interior Renovation - $18 million

- Renovation of 150,000sf of classrooms, kitchen, cafeteria space over 9
phases. School remained in session during the entire duration.

  • Sycamore HS - Natatorium - $9.7 million

- Complete demo of existing pool from roof all the way down to footers.
Installing new pool, super structure, and roof.

  • Sycamore HS - Interior Athletics - $5 million

- Renovation of 1st and 2nd floor locker room area, as well as
renovation of existing gym.

  • Sycamore HS - Football Field and Concession Stand - $4.2 million

- New concession stand, 3,500 seat football stadium, and parking lot
on the school grounds.

Project Engineer II

HGC Construction
03.2018 - 08.2021

Worked as on site Project Engineer for several projects. Supported the Project Executive, SR PM, and Superintendent. Responsibilities included:

  • Issuing change orders, RFI's, and submittals.
  • Assited SR PM with the monthly billings.
  • Update and maintain schedule.

Projects include:

  • Symmes Elementary - $9.8 million

- 15,000sf addition for new Pre-K and Kindergarten classrooms. Full
renovation of the existing 62,000sf school along with sitework that
added parking.

  • Tire Discounters Corporate Office - $5.5 million

- Full demo and renovation of 6 floors, totaling 33,000sf.

- Added a grand staircase in the middle that went from the first floor
all the way up to the 6th floor.

Education

Bachelor's Degree - Construction Management

Northern Kentucky University
Highland Heights, KY
12-2013

Skills

  • Phoenix Scheduling Software
  • Vista Viewpoint
  • pVault Accounting Software
  • Proficient in Microsoft Excel
  • Maintained great working relationships with contractors and owners

Timeline

Project Manager

Pepper Construction
09.2024 - Current

Construction Manager

Codell Construction
11.2023 - 08.2024

Project Manager

HGC Construction
09.2021 - 11.2023

Project Engineer II

HGC Construction
03.2018 - 08.2021

Bachelor's Degree - Construction Management

Northern Kentucky University