Supervised a 13- person team on an industrial project at GITI Tire, overseeing the installation of a new conveyor system, delivering the project nine days ahead of schedule. The conveyor systems spans the entire length of manufacturing area. This achievement is one that truly stands out to me. The hard work, dedication, and long hours invested throughout the process paid off in many ways, making this accomplishment especially meaningful and rewarding.
Maintain detailed shift logs and documentation to ensure accurate communication of equipment status, completed work orders while ensuring timely resolution of maintenance task.
B Shift Lead Electrician, train and mentor juinor electricians and new hires, providing technical expertise, safety guidance, and hands-on instruction to develope a skilled and productive maintenance team.
Troubleshoot and repair Siemens PLC-controlled machinery and Industrial automation systems.
Maintain Yaskawa and Lenze VFDs, motor controls, pumps, motors, and utility equipment.
Support robotic and automated material handling systems, including KUKA KR1 Robots, RGVs, LGVs, and collaborative robots.
Perform maintenance and repairs on Saurer Carpet Cabler Twisters, Heat set equipment, Conveyor systems, extruder, Balors, DA tank, RO unit, Boilers, Stretch Wrap Units, Winders, and depalletizing systems.
Maintain process and Sanitation Sewer lift stations, Transformer Containment Basins, Chillers, Air Washers, and compressed air systems to ensure reliable plant operation.
Install, and program HMIs on various equipment, program PLCs, and HVAC units.
Work closely with Workforce, workday, outlook, sharp, and Dozuki.
Perform maintenance and repairs on AC and DC power distribution, controo and automation circuits.
Demonstrate a strong commitment to safety by following all LOTO procedures, plant policies, and establish safe work practices.
Regularly attend First Day Back safety meetings and actively participate as a PEO Electrical Team member to support workplace safety initiatives.
Acsend performance materials produced nylon 6,6 polymer chips and spun them into various fiber types for different industries. Plants operations included: Bulk Continous Filament fiber for carpet, industrial fibers such as high-tenacity applications such as tire cord yarn and airbag fabric. My responsibilities included: Calibration, repair, and installation of all electrical and instrumentation equipment.
Troubleshoot and performing preventative maintenance to ensure equipment operates within quality standards and safety.
Diagnosing and fixing faults on equipment like; proximity sensors, controllers, Yaskawa drives, motor control systems, RTDs, Allen Bradley PLCs, and PLCs programming via Ladder Logic.
Installing new electeical and instrumentation equipment as needed, modifying existing systems to accommodate process changes or upgrades.
Documenting and Reporting; Maintain detail records of maintenance activities, repairs, and calibration. Completing work orders, and writing shift reports on equipment performance and potential issues.
Machinery worked on; Winders, Extruder, Draw Roll Machines, Draw Line, Balers, Boilers, Line Set machines, etc.
Safety Compliance; Adhering to all safety procedures related to plant, electrical and instrumentation work.