Overview
Work History
Education
Timeline
Generic

BRIAN K. JACKSON

Holdenville,Oklahoma

Overview

34
34
years of professional experience

Work History

General Foreman

Indian Refining
  • Installation of isomerization and HTU Units and refurbishing existing vessels and exchangers., Installation of Sulfur Recovery Unit with Amine and Scot Tail Gas Units.

General Foreman

Snyder Oil
  • Installation of 4 KCI Gas Compressors, Cryogenic Unit with Propane Storage, and refrigerate gas compression.

Pipe Foreman

Gas Company of New Mexico
  • Installation of new vessels and related piping and cooler for plant upgrade

Pipe Foreman

Conoco

Pipe Fitter

Kansas Power and Light
  • Installation of new coolers and Glycol unit also, removal of existing cooling tower for plant upgrades.

Pipe Fitter Apprentice

Conoco
  • Installation of Cryogenic unit.

Chief Inspector

Trans Western pipeline Company, San Juan, Expansion
01.2005
  • Oversaw the installation of one new solar 15,000HP Electric Drive compressor with Voith gear box and GE motor
  • Installed new Electrical Sub Station
  • Related piping at the Blanco Hub Meter station
  • Installed new meter runs for Conoco/Phillips.

Project Coordinator

TEPPCO
01.2004
  • P-35 expansion project in Indianapolis, Indiana.)
  • Installation of a 150,000-barrel liquid storage tank and associated piping
  • Installation of new fuel meter runs at several remote sites
  • Installation of 6 miles of 12” pipeline for product delivery
  • Installation of new liquid pumping station in Franklin, Indiana

Construction Manager

12.2021 - 05.2023
  • I have over 34 years of experience in the construction of pipelines and petro chemical plant facilities
  • That experience includes 25 years in the management of new construction projects, grass root projects, expansion projects, along with several other areas
  • I have experience on both sides of a project
  • I have worked in management for the contractor, as well as management for the Gas/Oil Companies
  • My experience includes small and large bore piping, civil work, building erection, gas compressor stations, pipeline management and inspection, pipeline routing and line placement, petro chemical, and process plants
  • Patriot Resources Incorporated
  • Managed construction on existing and new fields
  • Installation of new sales gas lines (both oil and gas)
  • Oversaw installation of new tank batteries, and new build pipelines from wells to tank batteries, as well as installation of new SWD lines and main loop lines

Chief Inspector

Energy Transfer, Deer, Station
12.2020 - 01.2021
  • Complete Demo of Oil Transfer Storage Terminal in Oklahoma City, OK, including all civil, mechanical, and electrical
  • Responsible for overseeing general contractor for all removal activities, to restore site back to natural pre-existing conditions.

Construction Manager

01.2019 - 01.2020
  • Work with Engineering and design for Proposed 42” Crude line from Nederland, Tx to Cameron Parish, Louisiana
  • Up front work with basic design and routing.

Construction Manager

Energy Transfer
01.2017 - 01.2019
  • Crude Line Lake Charles, La to St James, La, including the Atchafalaya River Basin

Construction Manager

01.2016 - 01.2017
  • Energy Transfer (Trunkline Gas Backhaul Project, FREC Regulated)
  • Installed large bore piping, valves, and equipment to convert station to bi-directional flow (4 stations in Mississippi, Tennessee, and Illinois)

Construction Manager

01.2015 - 01.2016
  • Energy Transfer (ETCOP Project / DAPL)
  • Conversion of (334 miles of existing 30 inch) from Coldwater, Mississippi to Johnsonville, Illinois
  • Abandonment / Conversion of existing gas line to convert to crude, including replacement of new MLV
  • Removal of anomalies
  • Re-hydro test entire mainline segment
  • Installation of new launcher / receiver facility which included all existing compressor station bypass piping.

Chief Inspector

Sunoco Logistics
01.2014 - 01.2015
  • Granite Wash Ext Project)
  • Responsible for installation of new tank terminal and related pipeline facilities in Texas & Oklahoma.

Field Construction Manager

01.2013 - 01.2014
  • Energy Transfer (Eastern Gulf Crude Access Project-North Segment)
  • 40 miles of 30” new lay
  • Abandonment and conversion of 565 miles of existing 30 from Southern Illinois to south Louisiana
  • Line placement and routing of 40 miles / 30”

Field Project Manager

Enterprise Pipeline Products
01.2012 - 01.2013
  • Ethane Beaumont to Lake Charles-FERC Regulated)
  • Coordinate with all disciplines up front
  • Identify route locations
  • Line Routing 52 miles of 20 inch

Construction Manager

Florida Gas Transmission
01.2009 - 01.2011
  • (Phase 8 Expansion Project: FERC Regulated Package One-Panhandle Segment)
  • Installation of 130 miles of 42” & 36” pipeline thru south Alabama and the panhandle of Florida
  • PHMSA hydrotest on 53 miles of existing 36” in central Florida

Construction Manager

Transwestern
01.2007 - 01.2008
  • Pipeline “Phoenix Project” (FERC Regulated)
  • Installation of 256 miles of 42” & 36” pipeline including related metering facilities in central Arizona

Sr Chief Inspector

Florida Gas Transmission
01.2005 - 01.2007
  • Turkey Point Project, FERC Regulated)
  • Installation of new grass roots compressor station in Miami, Fl

Sr Chief

01.2004 - 01.2005
  • Inspector, Florida Gas Transmission Phase 7 Expansion for Florida Gas Transmission FERC Regulate
  • Installation of 26 miles of 36” pipe on the FGT west leg in the peninsula (Gulf Coast side of Florida)

Chief Inspector

Florida Gas Transmission
01.2002 - 01.2003
  • (Grass roots Compressor Stations-FERC Regulated)
  • Installation of three 7200HP Rolls Royce Power Turbines, and related equipment
  • Inspected over 15.5 miles of 26” loop lines
  • Added to the existing 36” main line in Tampa, Florida
  • Lowered 36” mainline at Mobile, Alabama River crossings.

Construction Site Manager

01.2000 - 01.2002
  • Responsible for the overall field execution of a specific construction project with specific emphasis on safety
  • Responsibilities included: site preparation, foundation installation, and setting of process equipment, piping
  • It also included the administering of subcontracts and final testing in accordance with applicable codes to meet customer acceptance requirements.

Construction Assistant

01.1995 - 01.2000
  • Responsible for assisting the construction site manager in the management and direction of the construction site to which assigned
  • Duties included, but not limited to application of safety policies and procedures in all areas of responsibility, supporting and assisting management in FOB planning, scheduling, and status reporting, and coordinating resolutions of construction, engineering, and vendor related problems
  • Maintaining marked up IFC drawings that accurately reflect all field modifications, maintenance
  • Distribution of drawings and specifications
  • Coordination and management of subcontractors
  • Implementing and directing the QA program for the construction project, field surveying
  • Replacement of the Resident construction site manager on short-term projects.

General Foreman

Lion Oil Company
01.1993 - 01.1995
  • Installation of SRU with Scot Tail Gas.

Pipe Foreman

Freeport Mc Moran
01.1989 - 01.1991
  • Built skid mounted Sulfur Recovery Unit with Scot Tail Gas and Amine Treating for shipment offshore.

Education

High School Diploma -

Timeline

Construction Manager

12.2021 - 05.2023

Chief Inspector

Energy Transfer, Deer, Station
12.2020 - 01.2021

Construction Manager

01.2019 - 01.2020

Construction Manager

Energy Transfer
01.2017 - 01.2019

Construction Manager

01.2016 - 01.2017

Construction Manager

01.2015 - 01.2016

Chief Inspector

Sunoco Logistics
01.2014 - 01.2015

Field Construction Manager

01.2013 - 01.2014

Field Project Manager

Enterprise Pipeline Products
01.2012 - 01.2013

Construction Manager

Florida Gas Transmission
01.2009 - 01.2011

Construction Manager

Transwestern
01.2007 - 01.2008

Chief Inspector

Trans Western pipeline Company, San Juan, Expansion
01.2005

Sr Chief Inspector

Florida Gas Transmission
01.2005 - 01.2007

Project Coordinator

TEPPCO
01.2004

Sr Chief

01.2004 - 01.2005

Chief Inspector

Florida Gas Transmission
01.2002 - 01.2003

Construction Site Manager

01.2000 - 01.2002

Construction Assistant

01.1995 - 01.2000

General Foreman

Lion Oil Company
01.1993 - 01.1995

Pipe Foreman

Freeport Mc Moran
01.1989 - 01.1991

General Foreman

Indian Refining

General Foreman

Snyder Oil

Pipe Foreman

Gas Company of New Mexico

Pipe Foreman

Conoco

Pipe Fitter

Kansas Power and Light

Pipe Fitter Apprentice

Conoco

High School Diploma -

BRIAN K. JACKSON