Result-oriented Maintenance Director effective at developing, coordinating and leading facilities maintenance activities. Decisive leader proficient in managing preventive, predictive, and corrective maintenance for facilities.
NFPA 70E
Rail spur replacement
Replacing our current out of service rail line with all new line and foundations, Coordinate contractors to come on site and start the planning of replacement., Organizing the capital project write up to receive the money for this project., Manage contractors on site with any issues arising during install.
Pellet mill replacement
Replacing our pellet mill with an update version that increased output by 75%, Coordinate contractors for the millwright and the electrical project., Write up permits for these contractors to do this work of replacing., Organizing the capital project write up to receive the money for this project., Manage contractors on site with any issues arising during install.
Crumble roll replacement
Replacing our current crumble rolls with a larger unit that increase productivity by 150%, Coordinate contractors for the millwright and the electrical project., Write up permits for these contractors to do this work of replacing., Organizing the capital project write up to receive the money for this project., Manage contractors on site with any issues arising during install.
Pneumatic system upgrades
Upgrading our current air system by doubling the capacity of CFM so the plant can operate at a more energy efficient facility, Coordinate contractors for the millwright and the electrical project., Write up permits for these contractors to do this work of replacing., Organizing the capital project write up to receive the money for this project., Purchasing equipment for this upgrade., Manage contractors on site with any issues arising during install.
Kameron Vance- Land O'Lakes Senior Engineer -(484)637-7156
Eric Palmer - Maintenance Manager at Autozone distribution center - (209)658-0905
NFPA 70E