Led coordination with superintendents, subcontractors, and field crews to maintain schedule alignment and resolve onsite issues across all work fronts.
Directed change management activities, ensuring scope compliance, budget accuracy, and proper documentation of additional work.
Oversaw all material and equipment procurement, ensuring timely delivery and alignment with construction sequencing.
Managed the full submittal and RFI workflow, driving timely review, approval, and distribution to all project members.
Completed and issued weekly reporting packages, including PF calculations, and earned-progress updates.
Prepared detailed change order support documentation, ensuring proper justification and traceability.
Provided schedule updates and progress inputs
Project Experience:
Valero – Port Arthur, TX
Orion – La Porte, TX
CPCHEM – Orange, TX
CP2 – Cameron, LA
Project Coordinator
Cajun Industries, LLC
06.2023 - 06.2024
Tracked and coordinated daily civil construction activities, ensuring field teams had accurate information, required materials, and updated schedules.
Managed project logs including materials, equipment, and delays
Maintained RFI, submittal, and document logs to support overall project controls
Project Experience:
Huntsman – Conroe, TX
DOW – Seadrift, TX
Project Engineer
Harvey-Cleary Builders
05.2022 - 06.2023
I executed pre-construction, construction, quality control, and post-construction responsibilities; developed budgets, estimates, and schedules for multimillion-dollar tenant build-out projects; managed the preparation and execution of the project closeout process; led the creation and tracking of submittals, schedules, change orders, and RFIs; and provided updated progress reports to clients and consultants.
Assistant Construction Manager Intern
Toll Brothers
05.2021 - 08.2021
I oversaw and certified the quality control of subcontractors, monitored the construction progress of million-dollar homes, coordinated with homeowners to resolve warranty items, and assisted with the final stages of construction and punch-list work.
Assistant Project Manager Intern
Dynamic Systems Inc.
05.2020 - 12.2020
I coordinated mechanical and plumbing construction on a 603,000-ft² building, oversaw the release of materials and equipment, and led the development of submittals, schedules, change orders, and RFIs.
Education
Bachelor of Science - Construction Science, Business Minor