I am a self motivated team player. I can easily fit into any team and become an asset to the project. It is very important that I create and establish a workflow where we are not only be under budget and on schedule, but consistent as well.
Collaborated with senior superintendent and project management team to coordinate daily field operations.
Coordinated with subcontractors and vendors to maintain workflow on schedule.
Conducted daily quality control and safety inspections.
Documented daily field activities using logs and photos in Procore.
Developed and managed a three-week look-ahead schedule using Microsoft Project to sustain workflow.
- Over 3 years of experience in execution of multifamily construction projects. The
projects consisted of multi scope interiors and full exterior renovations and
additional amenities around the property.
- Extensive communication between project manager and project coordinator
through daily logs and emails and spreadsheets.
-Daily/weekly updates to the customer with photos, Notes and even safety
toolbox meetings to reassure customers of safe work culture on their properties.
- Understanding of specs, scope and plans in order to ensure the project is
running correctly and efficiently.
-Directed teams of subcontractors across various trades to ensure high-quality output.
-Ensure comprehensive documentation for project reports through procore.
-Perform managment walks to obtain certificates of completion on unit turnover.
-Managed logistics operations and maintained project inventory.
-Constructed and revised Excel spreadsheets to ensure alignment with ongoing work scope and budgetary constraints.
-Proactive problem solving
-Safety minded
-Quality Control
-Team oriented
-Leader mindset
-Detail Oriented
Alta Rochelle Nashville TN
-5 story 355 unit apartments (new construction)
-Wrap style project
-My responsibility is full-scope Amenity and clubhouse superintendent.
Alta Station Nashville TN
-4 story 302 unit apartments (new construction)
- Low-rise style project
-my responsibility was MEP and Interior finish superintendent.
Alta Farms Antioch TN
-3 story 330 unit apartments (new construction)
-Garden style project
-my responsibility was framing and interior finish superintendent.
AltaUnion Nashville TN
-4 story 283 unit apartments (new construction)
-Low-rise style project
-my responsibility was exterior superintendent
AltaFoundry Nashville TN
-5 story 223 unit apartments (new construction)
-Wrap style project
-My responsibility was Framing superintendent
Belcourt Property Renovation
10/2016 - 12/2017
-Complete repaint 480 units over 30 buildings.
-Demo old roof and add new Architectural to 30 buildings this includes installing
new flashing drip edge and vapor barriers .
-Demo all siding and Trim, repair all water damaged framing, and apply house
wrap. Replace with new Hardie siding and trim.
-Reseal floors of 480 wood decks.
-Replace all chimney caps, drip edge, and flashing with custom metal on all
buildings.
-Replace all gutters and downspouts on all 30 buildings.
-Fitness center and parking expansion at the Clubhouse.
-Replace metal Handrails at decks of 480 units and all breezeways.
-Replace all exterior lighting across the property including sconce lights and flood
lights.
- Replace All windows and Sliding glass doors at 480 units.
-Seal Coat full property.
Dunwoody Exchange deck repair
03/2019 - 10/2019
Removal of Lead paint/ metal decks across the property, and replaced with
pressure treated wood and stained.
Porterdale Mill Lofts
02/2018 - 05/2018
-Completed Tuck-point on 100 year old Mill turned into Lofts.
-Replace all broken bricks along the exterior of the building and fill all voids to
seal the building.
- erected scaffolding along the front of the building and swing stage scaffolding
was used along the rear due to the back of the building connecting to a river with
no ground access.
Terraces At Fieldstone
01/2017 - 09/2017
-Complete Paint on all 20 buildings over 250 units.
-Clubhouse remodel included full interior and exterior repaint. The walls in the
entrance were demoed to creat open floor plan.entrance were demoed to creat open floor plan.
-The Sauna at the fitness center was demoed framing was expanded and turned
into a package room.
- New windows and Storefront doors through the whole clubhouse.
- Gutters and downspouts on 20 buildings replaced.
- Laundry center renovation including new equipment, electrical, lights HVAC,
Plumbing and Countertops.
-New lighting and door hardware across 250 units.
-Demo old garden and concrete slab was poured and sealed to match existing
pool deck. Stone grill station installed on top.
Laurel Hills Preserve Roofing
06/2019 - 09/2019
• Replace new architectural shingles across all buildings.Multiple crews would run
boon lifts to execute the project.
• Replace all flashing and vapor barriers.
Forty-three 75 Multi-scope
09/2018 - 07/2019
-Convert Maintenance building into club room/ laundry room adding 2 bathrooms,
washers, dryers. The full building was upgraded to brand new plumbing, and
HVAC and electrical.
-The old laundry building was converted to a fitness center expansion.
-Seal coat full property.
-new 30x30 concrete landing with grill station and cedar pergola.
Jasmine At Winters chapel
09/2017 - 05/2018
-Complete paint at 40+ buildings including 2 clubhouses 2 laundry centers and 16
garage buildings.
-Convert old laundry room to New fitness center.
-Remodel clubhouse.
-Roofing repairs across all buildings including replacement of all flashing vapor
barriers.
-Replace garage doors in all garage buildings.
-Seal coat full property and re-stripe.
Fieldstone Glenn Multi-scope
10/2017 - 07/2018
-Complete exterior paint on 350 exterior units.
-Roof replacement across all buildings including clubhouse, Garages, and Mail
kiosks.
-Clubhouse interior remodel.
-Fitness center expansion.
-Dog park
- fall protection at all retaining walls
- build pergola at pool- build pergola at pool
Sweetwater Creek Clubhouse
05/2019 - 08/2019
-Complete interior and exterior repaint of clubhouse, fitness center and laundry
center.
-New Stucco walls on the exterior of the clubhouse.
-New Storefront doors at clubhouse Fitness center and the Laundry room.
-Remove walls in the interior of clubhouse to creat open floor plan and rewire all
electrical accordingly.
Stratford Interiors
10/2018 - 04/2019
-100 interior unit renovation.
-The renovation included
-New LVT flooring
-New lighting
-New cabinets
-New countertops
-New Interior paint
-New kitchen backsplash
-New blinds
-All hardware
Stratford Ridge Apartments
02/2020 - 08/2020
-100 units
Complete gut/demo and renovation of interior units including but not limited to
-new sliding glass doors requiring new flashing and waterproofing.
-demo old damaged sub floors and replace with new boards and float floors to
create proper sound proofing/ fire block and waterproofing.
- frame in new closets and add headers for new custom sliders.
River crossing Apartments
01/2020-08/2020
Complete interior renovation for 80 units including
-Major sub floor replacement in each unit due to sagging floors.
-Sliding glass doors replaced with new flashing and sealed due to water
intrusions.
-OSHA 30