Highly skilled Electrical Supervisor Cum Asst Site Engineer with 10 years of Gulf experience. Accomplished performing installations, maintenance and repairs on residential.Commerical,Highways and plant facilities. Recognized as results-oriented team leader with exemplary track record of success in quality control, planning and development and project management. Knowledgeable, hard-working Electrical Foreman committed to overseeing planning, scheduling and safety of crew. Proven track record running manpower on sites. Projects professional image with positive attitude, strong work ethic to effectively run jobs and teach others.
SITE Supervisor (FEB 2019 to 2021)
Projects. Umm Al Dome improvement project package 1
Sub-Contractor. Dorex Engineering
Main Contractor. Petroserv limited.
Consultant. ITAL
Starting Date. Feb 2019 to 2021.
Responsibilities
• Apply Permission to Work (PTW) application to the KAHRAMAA
• Submit Request for Inspection to the Kahramaa for each step of cable laying
• Apply shut down request to the Kahramaa
• Submit all the GIS to Kahramaa
• Testing and Commissioning of Service Cabinet for Traffic signal.
• Submit INR to the main contractor of all the work done at site
• Preparing daily, weekly and monthly site progress reports with photograph.
• Supervision of trench excavation, Sand bedding, Sand surrounding and
backfilling for HV and MV, LV tranches.
• Supervision of all Electrical works (MV, LV cable laying), Diversion of MV cable
and LV cable.
• Supervision of Street lighting works. (Installation of Street lighting poles 08m
single Arm,12m Double Arm,14m Double Arm,16m Triple Arm).
• Supervision of street light cable laying.
• Testing of MV, LV cables at site before installation and after installation.
• Making all the site reports and submit to the Kahramaa and Main contractor.
Arrange Jointers team for Jointing (MV, LV and Shut down Jointing) and report to Kahramaa
Project Job Title. LOCAL ROADS AND DRANGE PROGRAMME,
ROADS AND INFRASTRUCTURE IN DOHA INDUSTRIAL AREA.
Sub-contractor. Dorex Engineering
Main Contractor. QBC
Consultant Parsons Brinckerhoff.
Responsibilities.
• Supervision of Low voltage networking.
• Installation of Feeder Pilar, Service Cabinet.
• Supervision of existing and relocating low voltage networking.
• Supervision of existing streetlight poles and relocating the poles.
• Installation of Street lighting poles14m double Arm 400watt,12m double-Arm
250watt.
Maintenance Supervisor ,SAUDI ARABIA (KING FAISAL UNVERSITY AL HAFUF)
(From 16-06-2013 to 23-02-2014)
• Supervision of all HV substation and RMU.MV Room, Feeder Pillars.
• Installation of 13.8KV Package Substation MV/LV panels, Transformer, FP.
• Monitoring and supervising of small power & lighting including cabling, DBs.
• Supervision of MEP works in substations the Sub Contractor to execute the
project as per design, specifications and as per safety & planning.
• Investigate problem/issues at site and recommendation for the solutions.
• Inspecting the material delivered at site according the project Specification.
• Supervision of road street lighting and traffic signal works.
• Preparing daily, weekly and monthly site progress reports with photograph.
• Coordination with SEC for the inspection of shutdown and fitting inspection
including testing and commissioning.
• Coordinate with client and local Authority for electrical technical queries.
• Supervising for installation of RMU, Transformer, Feeder Pillar, HV Panel, and
package substation.
• Coordination with SEC for inspection of material and fitting inspection including
testing and commissioning.
Project: KFU PROJECT AL HAFUF and the Client was Saudi Electricity,
King Faisal University is one of the biggest university in Saudi Araba,In this
project all the 13.8KV (more than 50)Package substation have been dismantled
and demolished and energized new substations. And laid new HV cables for the
substations.
SITE SUPERVISOR, UNICON LIMITED DOHA QATAR
May 2008 TO 2012)
• Installation of Indoor, outdoor, package substation and pmt including HV and
MV switch Gear. (Siemens 8BK80,3AHS VCB,LUCY SF6 RMU).
• Responsible for HV MV, LV joints and terminations, Coordinate with
KAHRAMAA(QATAR ELECTRICITY).for the Substation shutdown work.
• Supervision of Kahramaa 11kV Package and Indoor/outdoor Substation
including, DB’s,HV panels transformer, Feeder pillars installation and fitting
inspection.
• Supervising for MV/LV & pilot cable jointing and termination.
• Supervising of 11kV, LV and pilot cables pulling.
• Coordination with Kahramaa for the inspection of trench for cable laying.
• Coordination with Kahramaa for inspection of material and fitting inspection
including testing and commissioning.
• Supervising the Installation of High Mast, Street Lighting, Bridges and Under
Pass Lighting.
• Monitoring site daily progress and site issues of work and report to project
manager.
• Coordination with Kahramaa for the inspection of trenches, cable laying, fitting
inspection and shut down.
• Supervision of trench excavation, Sand bedding, Sand surrounding and
backfilling for HV and MB LV tranches.
• Supervision of cancellation and dismantling the substation and change the load
to another substation.
Projects: Kahrammaa project GTC 291, Testing and commissioning of 11KV indoor S/STN.
• Mesaieed Housing for QP (32KM Cable laying and energized 42nos of 11 KV
substation.
• Gabor Berth with QP Installation of High Mast Poles 11Kv switch Gear
• Barwa City Development Project. Installation of Transformers, HV, MV
Switchgear, Feeder Pillar, Installation of street lighting poles (3m,4m,6m,12m)