Summary
Overview
Work History
Education
Skills
Timeline
Generic

Jacob Jordan

Springtown,TX

Summary

I have been working in the construction industry since 2018. I have worked as a construction crew leader and am now currently a CMT Technician. I have learned a lot while on different job sites and am always ready to learn more each and every day.

Overview

4
4
years of professional experience

Work History

CMT Technician

Riner Engineering
Fort Worth, TX
03.2021 - Current

American airlines fulfillment center

· Moisture condition fill and cap in building pad area to 12ft approximately 363,000 square ft

· Moisture conditioning consisted of testing Fat Clays

· Testing performed at least 6 hours per day

· Compaction testing in building pad areas = 1 test per 6-inch lift at 2500SF

· Lime pulverization, depth checks and compaction testing = 1 test per lift per 5000SF

· Compaction testing for utilities = 1 test per lift per 100LF

· Concrete cylinders were cast at a minimum of four cylinders per mix per day or one set of four cylinders per mix per 100CY, whichever was greater, on all pours.

· Pour testing consisted of Grade beams and Pier camps: 10 pours; Slab on Grade (383,000 SF): 23 pours; Ramp walls and slabs: 2 pours; Elevated Decks: 5 pours; Tilt Wall Panels, 25 pours; Private Paving (318,000 SF), 12 pours

Texport Logistics Center

· Moisture conditioning fill in the building pad area assumed 11-feet, totaling approximately 950,000CY. Fill placement duration was sixty-six days with monitoring performed on an average 11 hours per day.

· General Fill/ Retaining Wall Backfill in the paving areas assumed to be totaling approximately 40,000CY. Fill duration was ten days with monitoring on an average 11 hour per day.

· Compaction testing in the building pad area

· Lime pulverization, depth checks and compaction testing in paving areas

· Compaction testing for utilities

· Pour testing consisted Ramp walls and footing: 6 pours; Retaining Walls and Footing, 10 pours; Slab on Grade, 33 pours; Tilt Wall Panels: 12 Pours

Alliance Westport Business Park

· Moisture conditioning fill in the building pad areas assumed to be 11.7 feet, totaling approximately 861,850 SF. Fill placement duration was fifty-six days with monitoring performed on an average of 12 hours per day.

· Compaction testing in the building pad area

· Lime pulverization, depth checks and compaction testing in paving areas

· Compaction testing for utilities

· Concrete Pour testing consisted of testing 2 buildings, Ramps: 5 pours; Slab on Grade, 31 pours; Tilt Wall Panels, 12 pours; Dock Leveler Slabs and walls, 4 pours; Paving (795,000 SF) 29 pours.

· Straight Shaft Pier inspection, 500 piers drilled at approximately 8-foot penetration after bedrock was encountered.

AHS Rayzor Ranch Apartments

· Moisture conditioning assumed to be 14 feet, totaling approximately 76,000 SF. Fill placement duration was forty-five days with monitoring performed on an average of 10 hours per day.

· Compaction testing in the building pad area

· Lime pulverization, depth checks and compaction testing in paving areas

· Compaction testing for utilities

· Straight Shaft Pier inspection, 380 piers drilled at approximately 10-foot penetration after bedrock was encountered.

· Concrete Pour testing consisted of testing buildings and park garage, Slab on Grade: 6 pours; Elevated Decks, Columns, and Walls: 42 pours; Miscellaneous pours: 12 pours; footings: 25 pours; Retaining Walls: 10 pours; Paving, 10 pours.

Contruction Team Lead

DCS Construction
Fort Worth, TX
06.2018 - 03.2021
  • Coached team members in techniques necessary to complete job tasks.
  • Trained new team members by relaying information on company procedures and safety requirements.
  • Worked different stations to provide optimal coverage and meet production goals.
  • Evaluated employee skills and knowledge regularly, training and mentoring individuals with lagging skills.
  • Removed and replaced over-sized speed bumps for Texas Dept. of Transportation
  • Milled and resurfaced Loop 388 in South Odessa for Texas Dept. of Transportation
  • Performed numerous crack seals and seal coats

Education

No Degree - Criminal Justice

East Texas Baptist University
Marshall, TX

Skills

    Read and interpret construction plans

    Moisture Conditioning

    Performance of different testing needed

    Performance of inspections

    Concrete Pouring

Timeline

CMT Technician

Riner Engineering
03.2021 - Current

Contruction Team Lead

DCS Construction
06.2018 - 03.2021

No Degree - Criminal Justice

East Texas Baptist University
Jacob Jordan