I have been working in the construction industry since 2018. I have worked as a construction crew leader and am now currently a CMT Technician. I have learned a lot while on different job sites and am always ready to learn more each and every day.
American airlines fulfillment center
· Moisture condition fill and cap in building pad area to 12ft approximately 363,000 square ft
· Moisture conditioning consisted of testing Fat Clays
· Testing performed at least 6 hours per day
· Compaction testing in building pad areas = 1 test per 6-inch lift at 2500SF
· Lime pulverization, depth checks and compaction testing = 1 test per lift per 5000SF
· Compaction testing for utilities = 1 test per lift per 100LF
· Concrete cylinders were cast at a minimum of four cylinders per mix per day or one set of four cylinders per mix per 100CY, whichever was greater, on all pours.
· Pour testing consisted of Grade beams and Pier camps: 10 pours; Slab on Grade (383,000 SF): 23 pours; Ramp walls and slabs: 2 pours; Elevated Decks: 5 pours; Tilt Wall Panels, 25 pours; Private Paving (318,000 SF), 12 pours
Texport Logistics Center
· Moisture conditioning fill in the building pad area assumed 11-feet, totaling approximately 950,000CY. Fill placement duration was sixty-six days with monitoring performed on an average 11 hours per day.
· General Fill/ Retaining Wall Backfill in the paving areas assumed to be totaling approximately 40,000CY. Fill duration was ten days with monitoring on an average 11 hour per day.
· Compaction testing in the building pad area
· Lime pulverization, depth checks and compaction testing in paving areas
· Compaction testing for utilities
· Pour testing consisted Ramp walls and footing: 6 pours; Retaining Walls and Footing, 10 pours; Slab on Grade, 33 pours; Tilt Wall Panels: 12 Pours
Alliance Westport Business Park
· Moisture conditioning fill in the building pad areas assumed to be 11.7 feet, totaling approximately 861,850 SF. Fill placement duration was fifty-six days with monitoring performed on an average of 12 hours per day.
· Compaction testing in the building pad area
· Lime pulverization, depth checks and compaction testing in paving areas
· Compaction testing for utilities
· Concrete Pour testing consisted of testing 2 buildings, Ramps: 5 pours; Slab on Grade, 31 pours; Tilt Wall Panels, 12 pours; Dock Leveler Slabs and walls, 4 pours; Paving (795,000 SF) 29 pours.
· Straight Shaft Pier inspection, 500 piers drilled at approximately 8-foot penetration after bedrock was encountered.
AHS Rayzor Ranch Apartments
· Moisture conditioning assumed to be 14 feet, totaling approximately 76,000 SF. Fill placement duration was forty-five days with monitoring performed on an average of 10 hours per day.
· Compaction testing in the building pad area
· Lime pulverization, depth checks and compaction testing in paving areas
· Compaction testing for utilities
· Straight Shaft Pier inspection, 380 piers drilled at approximately 10-foot penetration after bedrock was encountered.
· Concrete Pour testing consisted of testing buildings and park garage, Slab on Grade: 6 pours; Elevated Decks, Columns, and Walls: 42 pours; Miscellaneous pours: 12 pours; footings: 25 pours; Retaining Walls: 10 pours; Paving, 10 pours.
Read and interpret construction plans
Moisture Conditioning
Performance of different testing needed
Performance of inspections
Concrete Pouring