
Having worked both in Engineering (10 years) and Construction (14 years) disciplines during my career with Bechtel, I’ve strengthened my ability to work independently and execute responsibilities with precision. I consistently focus on doing things right the first time, eliminating rework, and saving both cost and schedule while maintaining high standards of safety and quality. I collaborate closely with craft personnel to share knowledge and experience, ensuring smooth execution of field activities. This approach played a significant role in the successful construction completion of PCAAP, BGCAPP and Vogtle 3 & 4 as well as project completion activities prior to transition of Savannah River Site (East Hill Upgrades and Saltstone Disposal Units Project) and NAS (all mechanical/piping activities) at Arnold Airforce Base to new contractor and ML2 (Mobile Launcher 2 at Kennedy Space Center).
Oversee the final phase of the project, focusing on ensuring a seamless transition from construction to commissioning, handover, and operation. My responsibilities have centered on the coordination and management of key activities to achieve project milestones efficiently. Worked closely with engineering, construction, and commissioning teams to align turnovers with scope drawings. This alignment ensured that all project activities were properly captured and that the overall project schedule remained unaffected. In collaboration with the turnover coordinator, I was responsible for compiling, tracking, and resolving outstanding items found on punch lists. These included equipment installation issues and documentation errors. Through diligent compliance and proactive management, we achieved Mechanical Completion and attained Ready for Commissioning status ahead of schedule, demonstrating a strong commitment to project goals and operational efficiency. Partnered with the engineering team to address details for items missing from the scope drawings during both the design and construction stages. This involved reviewing drawings, coordinating design clarifications, and implementing necessary changes to prevent these gaps from impacting the turnover systems and to maintain the integrity and schedule of the turnover process. Collaborated with the piping and mechanical teams to ensure that all requirements outlined in the Subsystem Verification Matrix were met, including those regarding critical dimensions. This thorough approach helped guarantee that all aspects of the project conformed to the required standards and specifications. In partnership with the commissioning group, I contributed to the development of guidelines for turnover requirements based on lessons learned during the first turnover. These guidelines provide both teams with a clear framework, helping to facilitate future system turnover without the need for corrections.
Worked independently with limited oversight as the lead field engineer on the night shift. Coordinated closely with my supervision counterpart, field engineer, and field engineer tech to ensure consistent communication and alignment among all team members. Effectively communicated technical requirements to craft professionals, ensuring clarity and understanding. Coordinated with engineering on design issues related to piping and mechanical equipment systems. Took responsibility for reviewing design specifications, ensuring they were met, and promptly addressing any discrepancies or concerns that arose during implementation. Provides field engineering support and assistance to superintendents, supporting verifies material, equipment and quality, and assures results meet design requirements. Initiates requisitions for field purchases. Performed reviews of engineering design, resolves issues with design engineering which impacts construction installation activities. Validate all night shift quantities assuring installation is complete per specification, procedures, vendor manuals and technical data. Before moving to the night shift, I helped field procurement inspect and receive piping and pipe support materials. I reviewed 90% of the commodity module chase for installation, resolved engineering issues, and ensured no costly delays occurred with the erection of the chase on the modules up to 377 ft tall. Assisted the responsible piping field engineering located in MOD Yard get back on track due to being behind schedule.
Execute assigned responsibilities with limited supervision. Assigned to assist with 3 systems design (RAW Water, Potable and Sanitary). This led to redesign two of the systems and completing one of the systems based on my previous design experience with underground piping. This helped with avoiding major rework during installation due to my experience gain working at the Waste Treatment Project (WTP) and Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP). Worked all permitted related systems with the engineering and site assuring all the state requirements are in compliance prior to installation due to experience gained working Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP) and Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP). Planned all the mechanical installation and testing packages for the Phase 2 project activities due to my experience gained working at Pueblo Chemical Agent-Destruction Pilot Plant (PCAPP), Blue Grass Chemical Agent- Destruction Pilot Plant (BGCAPP) and Savannah River Remediation (SRR). Coordinated and addressed previously planned outage with site operation, addressing all unknown that was not addressed, which led to postponing the outage. My anticipation led to a future date which avoided impacting the schedule operation annual testing due to my experience gain working at Savannah River Remediation (SRR). Completed all pneumatic and hydrostatic testing for first phase of project due to my experience gain working at Savannah River Remediation (SRR). Completed all mechanical activities from design to installation assuring that quality was achieved through close out of all mechanical packages in phase one of the project due my experience gains in construction completion of PCAPP, BGAPP, SRR, Vogtle 3 & 4.
Executed assigned responsibilities with limited supervision. Prior to start Hot Functional Testing/HFT (the last major milestone that validates Unit 4 systems readiness prior to fuel load). Completed all the preliminary measures required to achieve start of HFT such as adjusting of the constant load supports, snubbers, spring supports to design settings and all work required for completion related to Hot Function Testing. Walked down related piping systems associated with HFT to determine external cleanliness met the project procedure and pipe surface is not damaged assuring HFT was not affected and meet schedule. During HFT support all issues during the "heat up" of the system such as interferences due to the thermal expansion of the piping, adjustment of supports due to binding of hot pipes at supports or any other surprises encountered. Multiple disciplines HFT support for 1) Custom Arc on all ASME and Safety related systems activities; 2) Richmond County Constructors (RCC) on ASME, Safety and Non safety systems activities; 3) Construction Pressure Testing/Flushing (CTF) with restoration of systems and closure of work packages; and 4) Support Testing Control Center (TCC) on related Mechanical/Piping when assistance is required as the last Mechanical/Piping Field Engineer on Night Shift. Completed Hot Function Testing ahead of schedule. A total duration of less than 42 days, original scheduled was 46 days.
Executed assigned responsibilities with limited supervision. Point of contact for all mechanical/piping issues that need to be addressed and completed on both Unit 3 and 4 on Night shift from ASME/Safety and non-safety related items. Work assignments with limited supervision. Other activities include assisting Electrical, Civil/Structure and Instrumentation with closing of systems. 1. Walk systems down for closure, identifying work to go, design/construction installation conflict. This helps address the problem with design via ESR in a timely matter which help complete construction installation and closed out numerous work packages. 2. Work with craft on execution of work assignments which helps avoid rework and meet schedule and increase production. Work packages are checked to assure everything required for the job are all accounted for. Details required for jobs are highlighted assuring it is executed. 3. Provide oversight and inspection of field installation/modification activities. 4. Walkdown and validated work performed and enter quantities in Teamworks. 5. Instrumental with closing all the open welds for the mechanical, electrical and civil group working with the craft. Currently closing all electrical welds that requires final visual inspections for closure of welds that allows the close out of the electrical work packages. “Go to guy” when there are issues with welding related issues with field supports that affects work packages that requires closure per the construction schedule. 6. Completed all the related work leading to hot function testing (HFT) for Unit 3 and all the adjustments required during hot function to complete the process. The HFT was completed per the schedule which is now closer to being operational with no mechanical issues.
Executed assigned responsibilities with limited supervision. Worked on the Saltstone Disposal Units Project at the Savannah River Site which consists of six 32-million-gallon tanks which will be utilized during the immobilization of low-level nuclear waste. The second of the six tanks is under construction with groundbreaking on the third and fourth tanks underway. Working assignments included develop a design input/design output matrix (Deliverable), Construction Turnover (CTO) preparation and approval process, Operations Acceptance Checklist (OAC), Start-Up (SU), Readiness Assessment(s) (RAs) process for SDU7. This scope required the utilization of my design background to develop a design input/design output matrix. Additionally, I identified and resolved any design input/output conflicts with the Design Engineering group to avoid impacts to the project schedule. An independent audit was completed on the design input/design output matrix, no issues were found. Utilized my construction background to develop the schedule for construction turnover sequencing and turnover packages to assure all scope is completed and documented following the logical installation per the project schedule. This sequencing will ensure no adverse effects to the project schedule while allowing Project Management to pursue the correct actions should any unforeseen situations arise. Worked with the operations team to define the contents of the Operations Acceptance Checklist (OAC) for the turnover of the completed project and ensure sufficient time has been allotted in the project schedule for completing the Operational phase of the waste tanks Facility Administrator Responsible for getting the New Construction Facilities for supporting the Saltstone Disposal Unit Project from a construction to an operation stage for occupancy. This required compliance with the required codes and permits for occupying the facility.
Planned, reviewed packages for constructability for installation to avoid rework and exposure to radiological and chemical hazards during routine and outage work of systems to implement modification or repair, upgrades and testing. Assigned major and complex projects which played a major part of the day to day operation of the facility therefore executing the work and avoiding rework played a major factor in operation of the facility. Completed the Tank Closure Cesium Removal (TCCR) Project which including fabricating/testing the new pump for replacing the old pump inside of the existing tanks, testing of the 3 transfer hoses (275 ft. each) and installation of hoses on supports and the shielding boxes which tied the Ion Exchanger Skid to the existing underground tank connections. The scope also included modifying the well water, domestic water, instrument and plant air to support the operation of the skid. Met the Schedule Completion date Completed the Chromate, Air and Water Systems Temp Mod installation for the preparation of the Utilities upgrades. Met the Schedule Completion date Completed the first phase of the East Hill Upgrades which included a 200 ft pipe bridge, along with 54 ft pipe rack with an elevation difference of 28 ft and a 28 ft trench for installation of 8 pipe system. The piping on the bridge was installed on 5 individual modules on the ground, put to together as 2 segments consisting of 2 spans (Long Span and Short Span) and then installed up 50 ft. Completed ahead of sch. Completed the installation of the 2" drain lines from the Mercury tank to the new fabricated Sample Cabinet for the Evaporators. The line size change from ½” to 2” due to the build up mercury which cause blockage in the 1/2" drain pipe, therefore the existing drain nozzle on tank was modified to accommodate the new installation of the 2” drain lines. Met the Schedule Completion date
Supervised two independent groups which consist of 6 Piping Field Engineers and 5 Mechanical Field Engineers. Changed the culture of both groups from a reactive to a proactive approach. Issues were addressed early for resolution that the Construction schedule was not impacted. Both the pipe and mechanical group met the turnover schedule for Construction Completion. Piping Field Engineer Utilized design experience in identifying and taking ownership of field installation issues and proactively communicating solutions to Design Engineering, thereby minimizing impact to field installation schedule. The solutions were communicated to Engineering via Field Change Request and Field Change Notice to allow the execution of the design changes in a timely manner to meet construction schedule. Performed walk downs and constructability reviews of proposed installation/modification design. Provided oversight and inspection of field installation. Performed material take off for installations/ modifications. Completed the Boiler Room in the Utility Building, Balance of Plant which includes all the Tank Farms, SCWO Building, Assigned Areas in MDB ahead of schedule with no punchlist items that affected Construction turnover to Startup.
Worked dual roles as Piping Field Engineer and Plant Design Layout Designer Identified and Resolved numerous conceptual design issues during design phase avoiding negative impact to construction schedule. Sole PDS equipment layout designer on PCAPP. Responsible for lay-out of all new equipment and buildings on site. Coordinated the reviews of Plant Design deliverables with the other engineering disciplines and other project functions. Redesigned and laid out the entire piping and equipment systems in the Breathing Air Equipment Room and Sprinkler Room. Resolved all the HVAC configuration and interferences issue with the HVAC subcontractor. Instrumental with all the penetration details in the Agent Processing Building(APB). Construction- Piping Field Engineer Piping field engineer for the entire Enhanced Reconfiguration Building and Southside in Agent Processing Building(APB). Completed the installation of piping in the entire Enhanced Reconfiguration Building (ERB) for the completion milestone. Piping field engineer for the Reverse Osmosis Water System. Redesign 50% of the piping system and 90% of the supports in the field due conflicts with design affecting the installation of design via Field Change Request and Field Change Notice to allow the execution of the design changes in a timely manner to meet construction schedule.
Laid out piping, reviewed design inputs, and resolved technical issues that affected assigned piping systems. Performed special studies on piping and equipment changes required by other disciplines . Created and updated the AZOT (Alex Zavoico Offline Tracking Tool) for assigned schedule activity charge codes. Coordinated and resolved equipment related issues. Reviewed equipment design input (vendor drawings, data sheets, equipment drawings, etc.) for assigned group. Developed and maintained equipment tracking database. Modeled and checked equipment. Responsible for all equipment placed in the model. Updated General Arrangement and Equipment Location drawings.
Revised original hand drawings from the early 1970s to AutoCAD. These drawings included mechanical parts, schematics, and PC boards Generated ECO's (Engineering Change Orders) in support of Engineering change directive and incorporated them. Maintained drawing database which contained released and unreleased drawings Performed other duties as assigned by supervisor.
Played a significant role in the successful construction completion of PCAAP, BGCAPP and Vogtle 3 & 4 as well as project completion activities prior to transition of Savannah River Site (East Hill Upgrades and Saltstone Disposal Units Project) and NAS (all mechanical/piping activities) at Arnold Airforce Base to new contractor and ML2 (Mobile Launcher 2 at Kennedy Space Center).