Dynamic Assistant Project Manager at SOLV Energy with a proven track record in project documentation and budget tracking. Skilled in Microsoft Excel and project scheduling, I excel in resource utilization and team collaboration, ensuring timely project completion and quality control. My innovative DFR template significantly enhanced project efficiency. Also, using P6 for scheduling, building the templates to present, and using Procore.
I assisted my project manager with the completion of both Substation and Transmission Lines, which included.
Complete documentation, organization of permits, test reports, daily reports, and meetings with PG&E.
Owner of the substation will go over the completion date and energized date, and will also create an Excel spreadsheet.
Sheets for procurement, material tracking, and budget are also using Bluebeam for RFI or redlines.
blueprints. That great accomplishment of mine was my DFR template and getting the substation.
Energized transmission lines are very important. I also used P6 for scheduling 3-4 week look-aheads to present to the owner of the substation and the utility company. Some of the software that we utilized were P6, Bluebeam, Microsoft Teams, Word, Excel Spreadsheet, Oracle, and Procore.
All commercial electrical installations use 1/2 to 1 1/2 EMT, and all breakers are on 120V, 220V, and 480V Square D and General.
Electric also seems single pull and double pull. Also, all MC cable 12/2 and 14/2, and all low-voltage cameras.
Systems include Pelco's, all Cat 6 and Cat 5 patch panels, punch downs, fiber AP systems, as well as speaker and fire alarm systems. Also, doing panel upgrades with Square D.
Charging HVAC system wiring, thermostat systems, cutting in collars, running ductwork and ventilation, and strapping up ductwork.
Duct work is running condensation PVC, and I am also adjusting the gas, replacing the spring in the system for elevation level.
Running a fart fan flex line set for a mini-split system, running threaded pipe, and threading pipe, as well as setting AC disconnect boxes.
We are a commercial and residential electrician company, also setting up Generac generators, and Cummins generators.
Also setting utility poles, and setting a Square D panel on the utility pole with 8 AWG aluminum wire we drilled and set with PG&E, along with weather heads, a Square D panel, and breakers. We also handled any homeowner calls regarding replacing breakers, switches, receptacles, and fans.
Conduit runs, bending, setting square D panels, and breakers are setting up Tesla charging stations, the mega stations.
Mega Packs for solar storage and the Tesla solar array are built, running all wires, and terminating in the subpanel. We also handled all racking systems, Iron Ridge, followed by wire management.
Heavy equipment operator for Local 3 union for fire cleanup in Santa Rosa and Mariposa County fire.
Received Hazwoper 40 training, respirator training, and operator certification for skid steer and excavator. I had to go through Cal Fire training and classes on a daily basis.
Ironworker Apprenticeship 155 in Fresno received OSHA 30 and 10 training, rigging certification, and welding certifications, as well as crane work and rigging.
Welding is working on the high-speed rail structural and reinforcing.