Experienced Project Manager and Engineer with a strong background in heavy civil construction, including state, local, design-build, and private sector projects. Proven ability to manage complex infrastructure and utility work, including bridge construction and demolition, traffic control, paving, boring, and railroad right-of-way operations. Skilled in project planning, scheduling, budgeting, and compliance with engineering specifications. Expertise includes contract negotiation, financial forecasting, change management, and cross-functional coordination. Committed to safety, quality, and delivering projects on time and within budget.
Oak Street Stormwater Improvements | Fort Collins, CO | $36M
Led a major stormwater infrastructure project under the Downtown Stormwater Improvement Program (DSIP) to mitigate urban flooding. Scope included 9,900+ LF of storm mains (18"–78"), lateral extensions, three tunnels (70–487 LF), utility relocations, and open-cut installations. Oversaw floodplain construction, permitting, traffic control, BNSF coordination, groundwater management, and full streetscape restoration. Managed stakeholder communication, business/residential access, and urban site logistics.
Sunset Village Residential Development | Erie, CO | $18M
Directed land development for a new residential community, including sanitary, storm, and water utilities; mass earthwork; pond construction; concrete structures; and full roadway buildout. Managed project scheduling, submittals, RFIs, pay applications, quality control, inspections, and jurisdictional coordination with the Town of Erie and client representatives.
Weld County Road 5 Widening & Raw Water Line | Erie, CO | $8M
Managed dual-scope project: raw water line installation and phased roadway widening near active schools. Oversaw utility work, erosion control, traffic management, and coordination with multiple contractors and utility providers. Delivered on-time completion through phased planning, stakeholder meetings, and third-party inspections.
United Fulton Augmentation Station | Fort Lupton, CO | $4M
Installed 10,266 LF of 30" ductile iron water line, including five bores (97–185 LF) under roads and ditches. Managed railroad coordination (UPRR), permitting, 24-hour boring operations, and open-cut ditch work with steel casing, flash fill, and clay cutoff walls. Delivered complex utility work under strict regulatory and environmental constraints.
Hamilton Construction Co.
Project Engineer / Acting Project Manager
Evans & Patterson Creek Fish Passage | King County, WA | $12M
Supported removal of four fish barriers on SR 202 and reconstruction with fish-passable structures. Responsibilities included permitting, design coordination, and oversight of grading, drainage, erosion control, and environmental compliance.
US 24 Resurfacing & Structural Improvements | Colorado Springs, CO | $11.5M
Assisted in resurfacing 10 miles of US 24 and structural bridge improvements. Scope included milling, paving, guardrail replacement, scour prevention, drainage upgrades, and traffic/erosion control.
SH 60 Bridge Replacement | Milliken, CO | $2M
Supported construction of a new bridge over the South Platte River, including demolition, channel improvements, traffic control, and river diversion. Oversaw plan reviews and field coordination.
8th Street Bridge Replacement | Loveland, CO | $2M
Acted as Project Manager for bridge replacement over Big Barnes Ditch. Managed demolition, new structure installation, traffic control, utility coordination, and critical crane lifts. Ensured timely completion ahead of irrigation season through close coordination with the City and ditch company.