Highly skilled and seasoned construction professional with extensive expertise in construction management. Demonstrated ability to provide overall administrative and technical oversight for diverse multimillion-dollar assignments globally. Strong focus on budget, schedule, safety, and quality, while also possessing a keen eye for value engineering opportunities.
Overview
20
20
years of professional experience
1
1
Certification
Work History
Superintendent / Civil Q/C Manager
Ameresco
01.2021 - Current
Construction oversight consisting of but not limited to; new Generation Plant installation with 2+ miles of underground electrical duct bank, (3) back-up Diesel generators, 72,000gal
Diesel storage tanks, new 12kv Transformers
Horizontal Directional Drilling of 12,000' of electrical duct bank installation under 2 sets of active R R tracks
Constant traffic control measures in place on active roadways
Ensured all materials compliant with relevant specifications / drawings
Superintendent
USCG Training Center
01.2022 - 01.2024
Responsible for overall construction of 15 Acre 5 MW fixed tilt ground - mounted array, 11.6MW Battery Energy Storage System, (2) 300Kw diesel generators, 12,000 gallon diesel fuel tank, Micro-grid Control System
Field management oversight of all specialty electrical and civil sub-contractors, with attendant Q/C responsibilities to ensure compliance with plans / specs
Extensive coordination with on base Security Forces and Facilities Engineering teams facilitating access for multiple oversized loads access to TRACEN
Coordinated base-wide outages over multiple weekends to allow high voltage work to continue
No safety incidents of any kind during construction
Safety parameters as defined by OSHA and USACE E M 385-1-1 safety manual
Compiled daily reports of progress - forwarded to the Contacting Officer's Representative and saved to Procore
Resolved subcontractor conflicts in interpretation of scope items
Superintendent
Patriot Construction Inc.
01.2019 - 01.2021
Superintendent overseeing new Brown-field ground-up Mental Health Care & Sleep Lab research building at San Francisco VA Medical Center campus
Direct responsibility of all personnel including self-perform and sub-contractor crews
Demolition of former structures within building footprint including all U/G utilities
Installed all new underground utilities, storm sewer, fire, and domestic water supply, electrical, gas, data & telecom security lines
Ensure all excavations comply with Cal OSHA / OSHA
3-week look-ahead schedule published weekly
MEP oversight of subcontractors
Construction Manager
Randstad Engineering - Energy Systems Group (ESG)
01.2017 - 01.2019
Managing multiple sub-contractors in support of extensive Energy Conservation Measures program at the V A Medical Center - San Francisco
Overseeing MEP subcontractors, coordinating with health care personnel in an active hospital / clinic environment
Many locations could only be worked during off hours or weekends due to the nature of the facility, requiring extensive outage coordination abilities
Remove and replace three Air Handling Units (AHU's) on top of four-story building using 500T crane
Replace components on 8 additional AHU's in the main hospital building
Install 107 steam traps and add new transmitters to tie-in to the building automation system
Install 2 new heat exchangers and associated piping / valves and controls, in rooftop mechanical room penthouses
Issued three weeks look ahead schedule to all stakeholders
Designated as the site SSHO (Site Safety and Health Officer) responsible for safety compliance with USACE EM385-1-1, VA standards, and ESG safety policies
Issue hot work permits for welding and cutting operations
Reviewed all crane lift plans prior to submission to the VA for approval of street closures
Supervised team of 14 construction workers to maintain productivity and quality of work.
Field Engineer / Site Manager
Insituform
01.2017 - 01.2018
Responsible for the company interface between local City, County, and Sewer District officials during a large Sanitary Sewer repair and Manhole rehabilitation in the City of Santa Rosa, CA
Coordination with 6 different subcontractors at 11 different work sites throughout the City, including but not limited to; private homes, schools, under major freeways, creeks, commuter rail lines, and City str
Conducted thorough site assessments to identify potential hazards, ensuring a safe working environment for all personnel involved in field operations.
Established rapport with clients by maintaining open lines of communication and addressing concerns promptly and professionally.
Managed team in troubleshooting efforts that alleviated errors.
Increased safety standards by enforcing strict adherence to industry regulations and company protocols.
Freelance Construction Consultant
Self-employed
01.2014 - 01.2016
Advised multiple rural 'Hobby Farms' and Equestrian Centers in Florida with property upgrades and code compliance
Upgrades included but not limited to the following;
Drainage interceptor trench placement and culvert installation
Electrical service upgrades to comply with NEC standards
New lighting installation in animal enclosures and common areas
Construction of new feed storage areas with abundant natural light
Installed plumbing upgrades to all animal waterer locations, interior bathrooms and animal wash areas
Senior Construction Manager
EnvivaBiomass LLP
01.2013 - 12.2013
Planned and managed late stage aspects of Greenfield construction of a wood pellet manufacturing facility
Prioritized and executed coordination of contractors with a focus on maximizing resources and meeting an aggressive completion date
Individual subcontractors were issued critical path tasks with redirected resources to achieve schedule compliance
As part of the Value Engineering the site grading plan was reviewed and modified to eliminate redundancies
Established a materials management program to properly receive, track, and store multiple shipments of high value specialty equipment supplied by worldwide vendors
Saved ~$850k by eliminating redundancies and inefficiencies in the site grading work {Retention Ponds, drainage ditches etc.} yet to be performed
Directed the overall field management of multiple subcontractors with a peak work force totaling 300+ workers on two shifts
Conducted extensive value engineering /cost reduction measures resulting in direct cost savings of $3.5+ million by enhancing schedule, aligning contractor focus, materials substitution
Accelerated the compressed schedule by streamlining the supply chain from multiple vendors /fabricators
Senior Construction Manager
SNC-Lavalin
01.2012 - 01.2013
Company Overview: International RTB- Bor, Serbia
Oversaw initial brownfield excavation, foundation, and soil work for a flash smelter furnace replacement and construction of a new sulfuric acid plant, with upgrades of various plant specific systems
Removed buried utility ducts, abandoned product, water, and drain lines from previous plant structures, including miscellaneous foundations
All voids were backfilled to specifications
Serbian Minister of Labor and area UN representative visited the site and complemented the staff on the project's progress
Introduced North American/European construction means and methods to local subcontractor workforce of 75 personnel
Implemented International Construction Safety Standards
Senior Construction Manager
Jacobs Engineering
01.2005 - 12.2012
Successfully managed the $700 million fast track dynamic Titanium Dioxide plant expansion project (Tampico, Mexico) in a live plant setting
Execution of technical evaluation of contractor bids for the initial project phases
Hired bilingual local technical/administrative staff
Coordinated contractor work fronts and integrated construction activities into existing plant operations
Tracked performance and presented status updates on construction progress
Construction Manager
Jacobs Engineering
01.2005 - 12.2012
Seconded to Abu Dhabi National Oil Company in this $1.1 billion multi-phase sour gas recovery project
Placed as team lead for Early Works portion of the project
Executed gas gathering-product pipeline systems
Addressed presence of significant amounts of H2s (23% mole) at well pad sites to limit workers' exposure during SIMOPS
Interviewed and hired core team including project, engineering, and electrical engineering managers
Volunteered for HSE Committee co-chair, and implemented a robust HSE program
Assessed multiple International contractors for work methodology / price / schedule
Site Construction Manager
BP
01.2005 - 12.2012
Company Overview: San Juan Coal Bed Methane, Major Project
Supervised all aspects of a $1.7 billion upstream program, with full responsibility over field decisions from HSE, QA/QC, field engineering, well site construction/ upgrade, materials management, and procurement departments
Credited for HSE turn around resulting in a nomination for the President's Safety Excellence Award for 97,000-man hours worked over 12-month period with no recordable incidents, no lost time cases
Increased client satisfaction survey scores from 87% to 93% over 12 months
Reduced per-well costs by 35% by optimizing resources and coordinating with BP on well site release locations
San Juan Coal Bed Methane, Major Project
Supervised team of 60 construction workers to maintain productivity and quality of work.
Oversaw successful completion of multiple projects simultaneously, prioritizing tasks based on urgency and importance.
Identified and resolved construction issues promptly to prevent delays.
Monitored daily progress on-site to maintain a clear understanding of challenges faced by the team members or any required adjustments in plans or schedules.
Established a reputation for excellent crisis management skills when unexpected issues arose during construction, quickly developing solutions to minimize project delays.
Monitored subcontractor operations and applied effective time, resource, and money management strategies to delivery under-budget project completion.
Supervised team of 65 construction workers to maintain productivity and quality of work.
Established and managed a branch office to facilitate growth effort in Pacific Rim
Grew operation in Okinawa and N
Japan from zero to $10+ million less than one year by engaging competent Japanese contractors for fast track civil engineering projects
Built personal relationships with USAF Base Engineering personnel
Executed aviation fuel infrastructure upgrade program at USAF bases, US Army installations, USMC facilities and US Navy fuel terminals in Okinawa and mainland Japan
New truck-fill stands installed at 6 different locations throughout Okinawa, including 2 on active flight line locations
Supervised, scoped and executed an $8.5 million structure lightning protection upgrade project to NEC standards within the highly restricted Munitions Storage Area