As a Senior Land Surveyor, I am a highly experienced and skilled professional with a deep understanding of the principles and practices of land surveying. I possess a strong background in both fieldwork and office operations, allowing me to effectively manage projects and teams from start to finish. With exceptional attention to detail and a commitment to precision, I am dedicated to providing accurate and reliable survey data that meets the needs of clients and stakeholders. As a natural problem solver, I am able to identify and resolve complex surveying issues, ensuring that projects are completed on time and within budget. Overall, my extensive knowledge, expertise, and leadership skills make me a valuable asset to any surveying team.
Project: Warehouses projects at Qatar Free Zone Authority.
Project: The pearl project (twin tower 24 stores)
● Control Surveying. Provides horizontal and vertical control.
● conduct 915 piles with different activities related to the work.
● Verify the Raft layout and concrete level, isolated foundation layout and level, column, structural work, block work, and ramps.
● Conducting measured building surveys; floor plans/elevations and sections.
● Supervising and controlling works carried out by sub-contractors
● Led and managed the contractor surveyor to improve their performance and work quality.
● Review the shop drawing for survey work.
● Verify the precast work setting out, alignment, and as-built.
● Landscape, planter box layout, irrigation system.
● Developing weekly and monthly reports for the project Manager.
Project: Msheireb Downtown Doha.
● Verify the accuracy of survey data, including measurements and calculations conducted at survey sites concerning daily inspections.
● Direct surveyors to the best checking procedures in order to increase the quality of work and reduce the time supervising the pilling layout, as built.
● Review of technical Drawings as per the design to prepare Layout for Curtain wall brackets, steel beam brackets, sliding Door, Auto sliding door and punch Window, cladding & steel structure works further to proceed for installation dept.
● Preparing data out of an Auto cad drawing for site layout horizontal vertical traversing to fix new control points & benchmarks checking & preparing as-built reports for existing structure in Cad Format Co-coordinating with Main contractor, supervisor & Engineers according to site conditions.
Project; LVQ (Warehouses ).
Project: Shahaniyah Camel Race Track LIMITED
● Check the natural ground levels, top-of-rock levels, design levels, and As-built.
● Record the results of surveys, including the shape, contour, location, elevation, and dimensions of land or land features.
● Calculate the / rock quantities from the survey data.
● Checking of Formation levels and Contour designs.
Project: Development of (4) sewage pump stations and water pipeline
● Check horizontal and vertical control points.
● Topographic working for the project.
● Check the alignment and level for the sewerage pipe.
● Setting out the pipeline.
● Calculation of volumes cut, andfill.
● Construction Surveying includes boundary surveys, as-built, construction layout surveys, topographic surveys, record surveys, mean high water line surveys
● Submit daily and weekly reports for the project manager and client.
Project: El Sewedy Cement Company
● Setting out the axes of the conveyor belt, check the level and verticality of support.
● Setting out for the cyclone of the preheater.
● Preheated Fan Line 2 (Leveling and Axes bases for the motors and fan casing and Padding works for all equipment).
● Filter Belt Conveyor – Pumps – Press Filter – Cyclones –Screw Conveyor).
● Setting out axes, level for the cement mill, bag filter, cement mill feed, and scrap belt.
● Check the anchor bolts' location.
● Verify the work from the civil company prior to starting the installation.
Project: Bungalows village.
● Established horizontal and vertical control points.
● Earthwork (cut & fill).
● Calculating cut and fill volume and preparing aninvoice for the subcontractor. ● Contour Map for theexisting level
● Setting out of the road alignment, structures such as buildings, lake, and landscape.
Project: Agrium Factory (water pipeline 12 km)
● Establish horizontal and vertical control points.
● Preparing profiles for the pipeline sections.
● Topographic survey for the pipeline track.
● Modify the pipe track as per site conditions.
● Setting out the pipeline, level, and alignment.
Project: San Stefano complex 32 floors (Egypt-Alexandria.
● Setting out for the block work first layer.
● Setting out for tiles axes and start point, tiles levels as per approved shop drawings. ● Setting out for road marking, parking, and curbstone.
● Landscape and hardscape.
● Level for marble floor installation.