A dedicated, outcome-driven, and proficient professional with an impressive track record, bringing forth extensive experience spanning almost 17 years. This journey has encompassed diverse international settings, fostering a wealth of expertise in Electrical Engineering. Holding a PMP certification, I have excelled in Project Management, emphasizing safety, quality, and productivity enhancement. My focus is on pursuing roles in the Shipyard Marine, Offshore, and Oil & Gas sectors, where I can leverage my skills to the fullest.
Major Projects
• Qatar Pride North Field Bravo Project (NFB) Client: QATAR GAS, awarded by Rosetti Marino, 1 jacket / 4 piles / 1
accommodation platform (6 levels including helideck) 90 personal (45 two man cabin) Amenities (recreation / gym /prayer
room / laundry equipment room / medical room & so on)
• Qatar Pride Bulhanine Project (BHN05) Client: Qatar Petroleum, awarded by: McDeromtt Eastern Hemisphere Ltd. (MEHL),
Major equipment Wellhead control panels / Totally closed motor propelled survival craft (14POB) / Telecommunication / fire &
safety equipment / switchgear & transformer
• Qatar First New Ship Building Project AL SAFLIYA Self-Propulsion Lift Boat for client GDI (Gulf Drilling International)
• MEGI (Main Engine Gas Ignition System) Project for LNG Rasheeda
• Over 200 LNG & LPG Vessels major Repair and Conversions
• Scrubber & BWTS new installation- Clients Nakilat & Maran Tankers
• BWMS Conversion Projects at 4 LPG Carrier and continue same for 14 upcoming vessels
• Oil Rigs ENSCO 96 / 97 Conversion Projects for client ENSCO & rest for GDI & Other clients
• World's powerful cutter section dredger and some other dredger major ships repairs
• Flying Squad Repair Jobs (Anchorage jobs) for LNG / LPG / Oil Rigs & tugs and all
Key Result Areas:
• Directing end-to-end operations across electrical section as necessary to ensure that jobs assigned to Section are completed in
a manner that is in accordance to job & safety requirements
• Supervising site activity & reviewed project schedule, ensured cost control within budget including planning for cash flow
requirements & so on; formulating duty roster and assigning Foreman/Engineer & Supervisor for each ship/project
• Scrutinized reference sheets to assess scope of hull work in each project for purpose of manpower & facilities planning & also, if
necessary, to initiate procurement & or preparation of materials
• Leading basic & detailed engineering & site supervision activities; worked on various proposals for Design of Electrical
Distribution System, Design Calculations, Evaluation of Offers, Drawing Reviews & Equipment Inspection
• Discovering sub-contracted jobs & raising quotations in consultation with Project Manager; appointing subcontractors in
consultation with Project Manager to execute jobs for which lump sum quotation is not required or either are not practical
• Guiding Foreman/Engineer to perform the jobs on his vessel/project so that he can raise works orders to appointed
subcontractors
• Attending Daily Stemming Room Meeting; identifying problem area & matters & notifying section about action to be taken
• Examining quality & safety measures; highlighting matters & precautions to be taken on vessel/project to Foremen/Engineers &
Supervisors
• Ensuring that jobs are accomplished with budgeted man-hours for section; computing cost & man-hours of each job; provided feedback
to Estimating Section any discrepancy between actual & quoted man-hours, thereby enabling them to update their Tendering System
• Evaluated tender documents of trade; recommended estimator on time schedule, foreseeable problem areas or difficulties in
performing jobs
• Supervised critical and urgent jobs on the vessels/projects in accordance with the work schedules issued, on- time projects completion, most projects completed with zero safety / quality incidents & zero reworks
Major Projects
• Polar Pearl / Barkly Pearl (BV Class Livestock Carrier)
• SLB2 & SLB3 (BV Class Submergible Barge)
• Patrovessel (BKI Class Indonesian Government Navy Vessel)
• Offshore Bulk Terminal Barge (OBT)- V11007/8 (ABS Class)
Team Size: Key Result Areas:8 engineers/8 supervisors & 200 subcontractor workforce from 7 nationalities directly• Directed complete electrical engineering works including design, procurement, pre-commissioning, quality control & on-site construction management of Marine & Offshore Projects• Designed:
o & analyzed engineering plans, specifications, project schedules, designs, circuit diagrams & estimates for construction &
maintenance of projects
o Subcontracts bills and work allocation as per contractual documents
o As-built drawing for final project hand-over
o & reviewed all electrical as-built documentation packages and inspection records
o Electrical equipment lists, load lists, data sheets, electrical calculations and cable schedules
• Inspected cable lay works, testing of LV & HV cables, tray routing, cable dressing, glanding & termination work
• Specified electrical procedures for installation testing & commissioning
• Led provisional acceptance testing activities to ensure electrical products/systems comply with project specifications,
electrical standards & customer requirements
• Ascertained timely delivery of various project drawings including one-line, three-line, block, schematic, wiring and connection
diagrams, equipment and cable tray arrangement layouts and electrical installation guides
• Organized & negotiated meetings with the electrical vendors and subcontractors for price finalization
• Established & sustained relationship with contractors, consultants, client, vendors, outside agencies & other staff
• Appreciated with successful project completion certificates and leadership skills development certificates from clients
Major Projects
• LB 1, ABS Class Accommodation Barge in PT. BRITOIL Shipyard, Batam, Indonesia
• VS 491 CD AHTS, Hull No’s - 7047, 7048 & 7050, DNV Classed Vessel in PT. Batamec Shipyard, Batam, Indonesia
Key Result Areas:
• Directed complete electrical engineering operations for project including design engineering, commissioning, installation &
testing with a team of 110 Electricians and Supervisors/ Foremen
• Prepared basic design of electrical installation; selected cable size considering various de-rating factors, voltage drop & fault
level calculation; analyzed electrical power requirement; selected capacitor banks; calculated earthing conductor sizing;
selected switchgear & rated various equipment
• Designed preliminary drawing, SLD, cable schedules, technical specification & data sheets; designed electrical drawings, project
schedule & progress report; reviewed engineering plans & specifications; spearheaded installation, testing & commissioning
of HT & LT panels, cables, transformers, DG sets, electrical systems, fire alarm & safety systems
• Scrutinized all as-built documentation packages & the records; reported design or installation issues to relevant yard & owner representatives; submitted complete commissioning report upon project completion
Key Result Areas:• Steered termination & testing of Electrical Control Panels & Protective Devices of Transformers, Alarm Systems & other Switchgear
• Ensured maintenance & servicing of Electrical Motors & Generators
• Directed installation of testing as well as site commissioning activities for smooth progress work
• Monitored electrical repair works in Vessel Conversion
PMP Certified
PMP
IOSH - Managing Safely
Root Cause Analysis
PMP