Over 10 years experience in Document Control Coordination and Turnaround which includes Quality Assurance, Information management, Major Project, Project Management and Record Management activities. Ability to prioritise and complete multiple tasks to achieve project goals
Overview
14
14
years of professional experience
Work History
Document Controller
Suncor Energy
Fort McMurray, Alberta, Canada
07.2021 - 01.2022
Received and reviewed turnaround IFC packages and update with comment in turnaround planning on hold packages log if any discrepancies
Upload IFC packages into the eB system by giving electronic stamp such as TA IFC and revision of package
Updated TA Job file tracking log for issue new IFC packages
Issued TA IFC packages to the contractors, TA managers and execution coordinators by email link
Received RFIs to process and generate RFI number for Open RFI and upload into eB
Received Closed RFI to update RFI log and upload into eB and issued as per distribution list
Received ITPs from contractors to review and update ITP log
Received and reviewed TA packages and upload into the eB.
Document Control Specialist
Syncrude Canada Ltd.
03.2021 - 06.2021
Received ITP from contractors for review and approval
Received approved ITP from QA lead and coordinators
Updated ITP tracker log and enter time stamp of received and approved ITP
Received singed off RR packages and update into the RR log and ITP log
Tracking and generate reports of signed off ITP and signed off RR for QA lead and manager.
Asset Information Management Coordinator
Suncor Energy
Fort McMurray, Alberta, Canada
04.2018 - 04.2020
Received and review turnaround IFC packages and update with comment in turnaround planning on hold packages log if any discrepancies
Received, reviewed and Issued TA IFC packages to the contractors, TA managers and execution coordinators by giving electronic stamp such as TA IFC and revision of the package
Upload IFC packages in live link and Updated IFC plant log and Planner's Dashboard
Received ITPs from contractors to review and update ITP log
Received RFIs to process and update RFI log and distribute as per distribution list
Generate RFI numbers from live link for Open RFI and upload Open RFI in to the live link.
Document Control Specialist
Syncrude Canada Ltd.
12.2013 - 12.2015
Received, distributed and tracked work packages including EWPs and CWPs
RFIs, FCNs distributed and documented as per the distribution matrix
Attained Projects Kick-off & Weekly Construction meetings
Supported Project manager, Construction Specialist and contractor as required
Received and quality assurance the As-built packages, sent to the coordinator and project operation group
Checked the status of as-built drawing into the TDocs
Assisted the project team with documentation turnover
Tracked all work packages from initial receipt through to As-built completion
Assisted the Project Manager for close out projects.
Document Controller
Nexen Inc
03.2013 - 07.2013
Printed IFC packages of various projects and quality assurance the package as per standard
IFC package discrepancies updated in the log and sent comments to the engineers
Updated the daily review project log and transmittal log
Created and issued the transmittal of CWP, EWP, FIWP, DCN & TDR to the engineers and contractors
Maintained and update the libraries according to the projects
Received and maintained the RFIs and redlines
Assisted engineers, contractors and planners for the inquiry about the project packages.
Asset Information Management Coordinator
Suncor Energy
Fort Mcmurray, AB, Canada
01.2008 - 02.2013
Issued the turnaround IFC packages to the contractors and engineers by gave electronic stamp such as IFC, Turnaround and according to discipline of the package
Performed quality assurance for controlled documents, such as correct document number, title, stamps, clouds and revision as per document control standard
Received the RFI to process to updated RFI log and distributed the engineers and contractors
Received the TDN and NCR to update the log and distributed the engineers and contractors
Assisted to planners, contractors and engineers for the issues of the packages
Scanned the turnover documents and recorded the log and uploaded in the live link
Generated the VP numbers for MRB and uploaded in the live link
Interpreted the report and send the comments accordingly to the EP house
Approved the cancel and obsolete assignments
Uploaded the redlines in to live link
Generated NER numbers through CERLL
Prepared documentation for Archive
Assisted Major projects with meeting requirements through document and data auditing, uploading, cross referencing the QA document and completion of project data
Requested the engineering tag number and drawing number for engineers
Received all FCNs and RFIs maintaining a log for each
Received all drawing requests and EWP package for copy
Assembled packages of documents for EWPs and CWPs
Audited documents and made corrections when needed.
Education
Diploma - Computerized Accounting and Office Administration
Concordia College
01.2006
Master of Commerce - Business Administration
University of Maharaja Sayajirao
Skills
Experience with Turnaround, Turnover documentation on completion of project
Excellent user of software systems: EB system, Live link and TDocs
Experience and knowledge of electronic records & information management system and terminology
Data entry skills and analytical detail oriented for qualifying checks of projects documents
Excellent user of Microsoft: Word, Adobe professional, Excel and outlook
Proven interpersonal, communication, organizational and multitasking skills
Proven ability to work within a team, independently with minimal supervision
Document Controller at Electro Velocity Industrial Contracting Company EVICCODocument Controller at Electro Velocity Industrial Contracting Company EVICCO
Document Controller at Electro Velocity Industrial Contracting Company EVICCODocument Controller at Electro Velocity Industrial Contracting Company EVICCO