Experienced and motivated Electrical Technician with experience in power generation at coal, natural gas, and solar plants. Devoted to keeping up-to-date with technologies, standards, and trade skills. Documented results with project management,team leadership, and electrical installation/testing.
Hired to install a 74.5 megawatt solar plant for FPL
Delivered Results
Hired to install a 75.5 megawatt solar plant for FPL
Delivered Results
Hired to install a 74.5 megawatt solar plant for Duke Energy
Delivered Results
I was part of a team that performed startup testing and commissioning in industrial power plants throughout Florida.
Delivered Results
● Commissioned system high/medium/low voltage transformers, switchgear, and motor control centers.
.● Installed and tested PLC, DCS, and other control systems for processes throughout the power plants.
● Performed startup and technical troubleshooting for motors, pumps, and other electrical-mechanical equipment.
● Installed, tested, and calibrated instrumentation critical to the power production process.
I was part of a team that performed startup testing and commissioning in industrial power plants throughout Florida
Delivered Results
Hired as an electrician journeyman to install a 45 megawatt solar plant for Duke Energy
I was promoted to Electrical General Foreman a few weeks after getting on the jobsite
Delivered Results
Hired to work on a 1800 megawatt power plant for FPL
(3 on 1 combined cycle)
Delivered Results
Hired as an electrician journeyman to install 75 megawatt solar plant for FPL.
Delivered Results
● Commissioned all inverters
● Installed dc feeders, ac feeders, and PV to PV module terminations
● Performed startup testing and technical trouble shooting for combiner boxes and inline fuse PV terms
● Energized combiner boxes and assisted with energizing inverters
Hired as Instrument Fitter to install a 52 megawatt wood chip burner
Delivered Results
Hired as an electrician journeyman to install 75 megawatt solar plant for FPL
Delivered Results
Hired as an electrical journeyman to install a 1140 megawatt power plant for Tampa Electric
Delivered Results