Highly skilled and motivated electrical engineer with expertise in power systems and electricity sector seeking a challenging position in the power industry. Strong technical knowledge, project management abilities, and a proven track record in electrical engineering. Committed to delivering efficient and reliable solutions to meet industry demands and contribute to the growth and success of an organization.
PV and BESS Energy Integration
Electricity Sector Utility Reform Project (ESURP) under World Bank; Associated with Electricity Distribution and Supply Authority (EDSA)
Completed the Reinforcement, rehabilitation and expansion of the primary 11kV medium distribution grid network equipment in selected locations in Freetown: Total 11kV underground cable installed=.18.8km Convert Old 11kV Underground Network to Overhead Line = 91.2km, Upgraded Low Voltage Distribution Network in Selected Communities = 215km, Replaced and Injected 11/0.4kV Transformer Substations = 131., Replaced Low Voltage outdoor distribution panel=107, Replaced 11kV Oil Filled Ring Main Units = 205.
Energy Sector Utility Reform Project Additional Financing (ESURP-AF) under World Bank; Associated with Electricity Distribution and Supply Authority (EDSA)
This project covers the rehabilitation and upgrading of the Freetown distribution network. Covers addition of 5 (Five) 33/11kV Primary Switching Stations (i.e., Aberdeen, Falconbridge, Cline Town, Jui & Waterloo), 33 kV & 11 kV network expansion, distribution substations, Low Voltage distribution network, Better Load Management at the 161 kV Pool Switching Station at Kingtom (Freetown) (additional 1x35/40MVA Transformer)
The Project for “Urgent Improvement of Power Distribution System in Freetown -Phase II & III Funded by the Japanese International Cooperation Agency (JICA) Associated with Electricity Distribution and Supply Authority (EDSA)
Phase II Construction of 33 kV Distribution Lines, Construction of 15 MVA Substation at Goderich, Construction of 11 kV Lines from Goderich to Sussex, Construction of 11 kV Lines form Goderich to Juba, Rehabilitation, and extension of 11 kV distribution substations to unserved communities in western Area
Phase III The Scope of works include Construction of 33 kV sub-transmission line (49.6km) from Goderich to Tombo, Construction of 1 x 15 MVA 33/11 kV Substation at York, Construction of 1 x 15 MVA 33/11 kV Substation at Tombo, Construction of 11 kV Lines (52km), Construction of 28 (twenty-eight) 11/0.4 kV secondary substations.
Enhancing Sierra Leone Energy Access Project (ESLEAP), World Bank; Associated with Electricity Distribution and Supply Authority (EDSA)
Provide new and improved electricity services to Nine (9) major towns and surrounding communities by capitalizing on the transmission lines under construction and the availability of electricity through import over the TRANSCO CLSG interconnection.
Preparation of Studies of Two Photovoltaic (PV) and Battery Energy Storage System (BESS) Plants World Bank; Associated with Electricity Distribution and Supply Authority (EDSA)
The Consultant tasked to develop concept design for the connection of 30MWac PV / 5 MVA BESS at Newton and 10 MWac PV / 5 MVA BESS at Lungi in Sierra Leone. The concept design represents a technical analysis and preliminary design of PV and BESS plant.
Elsevier (Energy Conversion and Management)
Integrated approach for optimal techno-economic planning for high renewable energy-based isolated microgrid considering cost of energy storage and demand response strategies
https://doi.org/10.1016/j.enconman.2020.112917
MDPI (Sustainability 2020) Journal
Demand Response Economic Assessment with the Integration of Renewable Energy for Developing Electricity Markets
https://www.mdpi.com/2071-1050/12/7/2653
MDPI (Sustainability 2019) Journal
Economic Analysis of Demand Side Management Considering Interruptible Load and Renewable Energy Integration: A Case Study of Freetown Sierra Leone
https://www.mdpi.com/2071-1050/11/10/2828
2018 IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC)
Unit Commitment Considering Uncertainty of Price-Based Demand Response
DOI: 10.1109/APPEEC.2018.8566295
IEEE 2018 ,Okinawa Japan
Future Smart Grid Operation Introducing Renewable Energy and Unit Commitment in Sierra Leone