Demonstrated success in pipeline construction, completing extensive projects while ensuring adherence to specifications and safety standards. Expertise in welding inspection and hydrotesting procedures supports effective project management, delivering results that enhance operational efficiency and reliability.
Completed 2 miles of 8" piping replacing old acetylene welded piping, using stopples at each end in Alma, MO. Conducted hydrotesting on 26" Line Q from Hesston, KS to Kansas City, KS, employing stopples and recapturing gas with Weldfit across 19 sites.
Put in 4 miles of 8" piping replacing Acetylene welded pipe, several HDD bores, new pigging facilities in Alma, MO. Replaced 12" piping with 4" piping and large HDD.
Working for Southern Star in Wyoming from Rawlins to Cheyenne: installing new valves, hydrotesting, and completing line w reversal upgrades, including new ultrasonic meters to enable station flow reversal.
Replaced double exposure on integrity digs where the pipe was exposed, and installed rock where needed, changed stream direction.
Constructed new launcher and pigging facilities on Line Q for hydrotesting capabilities.
Recoated Line Q in Lyndon, KS to enhance durability and performance.
Worked in Welda, KS installing more 30" pipe and eliminating two old lines that were replaced by the 2020 DPA project, installing more electronic valves for SCADA.
Went to Leavenworth KS, working at the Prison and inside Fort Leavenworth, removing old piping and putting in new pigging facilities. The prison was having work done to facilitate a new building complex.
Completed 32 miles of 36-inch new lay from Welda KS to Ottawa KS while coordinating with Gregory for blasting operations to clear hard limestone from row.
Installed two scrubbers and new metering tubes at Welda Station.
Replaced 30" lines and valves to enhance operational efficiency.
Executed installation of new equipment to improve system functionality.
Upgraded existing infrastructure at Welda Station for improved performance.