Results-driven project manager with extensive experience in refinery shutdowns and heavy industrial construction management. Proven ability to deliver projects on time and within budget, leveraging bilingual communication skills to enhance collaboration across diverse teams. Field experience encompasses a wide range of facilities, ensuring proficiency in all aspects of construction management. Recognized for consistently maximizing return on investment through strategic planning and execution.
Work History
Principal Estimator
2 Years 2 Months
FLUOR GOVERNMENT | 09.2024 - Current
Mechanical – Piping estimator
Program Manager
1 Year 10 Months
NOOTER CONSTRUCTION | 10.2022 - 08.2024
Managed all field construction activities, including estimating, schedules, cost, and subcontractors.
Managed daily operations and staff activities to ensure smooth workflow.
Chevron Refinery
Sr. Project Manager
NOOTER CONSTRUCTION | undefinedundefined
Managed field construction activities, including estimating, scheduling, cost management, and subcontractor coordination.
Oversaw daily management operations to ensure smooth workflow.
Collaborated with PGE (Portland General Electric) teams on project execution and delivery.
Field Operations Manager
1 Year 4 Months
INNOVATIVE CONSTRUCTION SOLUTIONS | 02.2021 - 06.2022
Managed field construction projects, including estimating, scheduling, costs, and subcontractors.
Directed field operations to align project execution with safety, schedule, and quality standards.
Coordinated crews, subcontractors, and site activities to maintain efficient workflow across active job sites.
Monitored daily field conditions and resolved operational issues to reduce delays and rework.
Maintenance Site Manager
3 Years 8 Months
SCHULTZ | 04.2017 - 12.2020
Managed E&I, new construction, civil, capital work, mechanical, turnarounds, and all related disciplines.
Performed cost estimating for projects to determine budget requirements.
Oversaw safety attendants during turnarounds to ensure compliance with safety protocols.
Grew account from $1M to $20M within one year.
Handled all aspects of day-to-day management.
Oversaw installation of structural steel and piping for SIS Project.
Facilitated project oversight for Valero Wilmington, managing a budget of $30M.
Project Manager
4 Years 1 Month
BRINDERSON CONSTRUCTION | 03.2013 - 04.2017
Chevron El Segundo, EPC Water treatment Plant $4.5M Project
Led operations of fabrication shop to ensure timely project execution, Pipe Field Installation, Schedule, Cost, Estimating and QA/QC, and Subcontractors
Oversaw project turnover and PSSR packages.
Phillips 66, NOx Reduction Project, Carson California $1M Project
Managing Fabrication Shop, Field Installation, Schedule, Cost, Estimating and QA/QC, and Subcontractors
Responsible for Project turnover and PSSR packages
Managing Fabrication Shop, Pipe Field Installation, Schedule, Cost, Estimating, QA/QC and Subcontractors Responsible for Project turnover and PSSR packages
Aera Energy, Multiple Projects, Central California (Brinderson, Project Manager-Senior Estimator)
Managing Fabrication Shop, Pipe Field Installation, Schedule, Cost, Estimating and Sales.
Project Manager
3 Years 5 Months
ARB | 10.2009 - 03.2013
SCE McGrath Generating Station, Oxnard, California $21M.
Project manager for 100,000 man-hours, managing cost, schedule, Union craft and subcontractors.
New construction for a generating station from ground up including all civil, mechanical, electrical, and miscellaneous disciplines.
Management of all fabrication and installation, which includes compressors, tanks, pumps, CS and SS piping, and structural steel.
Cameo Power Plant Grand Junction Colorado
Manager for 10,000-man hours, $1.5M Project managing Union craft and subs.
Estimating
Conoco Phillips Wilmington, CA Road 3 Storm Water Upgrade & Tank Farm Sleeves Penetration
Project Manager for 20,000 man-hours, $3.3M project managing Union craft and subs.
Managing pipe Fabrication and installation
Estimating
Tidelands Oil Production Company, Port of Long CA, Pipeline Relocation Project
Project Manager, project managing Union craft and subs. Managing pipe Fabrication and installation.
Southern California Gas Company, All of SoCal Gas Service Territory. Pipeline Integrity Transmission Work.
Project Manager, project managing Union craft and subs. Managing pipe Fabrication and installation.
Estimating
Sr. Project Manager
9 Months
HOBBS ENGINEERING | 01.2009 - 10.2009
LASCD Calabasas Landfill Project - Public Works - $20.5M
Project Manager for 80,000 man-hours, Estimating, managing cost, schedule, Union craft and subs.
New construction project including pumps, compressors, piping fabrication, structural steel, electrical and civil work.
NANDINA Water Treatment Plant - Public Works - $3.5M project, Estimating, managing cost, schedule, Union craft and subs.
Yucca Power Plant
Project Manager for 35,000 man-hours, $5M project, managing cost, schedule, Union craft and subs.
Project completed on schedule and ahead of budget with a 40% growth and 35% of profit margin.
Sr. Project Manager / Sr. Estimator
IRWIN CONSTRUCTION | undefined05.2007
Thumsco, Island and CO2 Plant
Construction Manager for 30,000 man-hours, $4.1M project, managing field supervision, project controls, and sub-contractors. Managing pipe Fabrication and installation
January 2009
Construction Manager
11 Months
JACOBS ENGINEERING | 06.2006 - 05.2007
Construction Manager for $100M new construction project, managing bids, scheduling, project controls group and sub-contractors.
Shell Refinery, Wilmington (Jacobs Engineering Construction Manager)
Construction Manager
2 Years 4 Months
JVI | 02.2004 - 06.2006
Conoco Phillips, Wilmington
Construction Manager, for 50,000 man-hours, $3.6M USD Project, Estimating, managing subs, field supervision and project controls group.
Project completed on schedule (Lump Sum) with 30% scope growth and 23% profit margin.
Grace Platform, Santa Barbara
Construction Manager, Managing labor and cost for Pre and Turnaround work.
Shell Oil Refinery, Wilmington
Construction Manager for $1.5M Carbonate Cracking Pipe project, Estimating, managing construction supervisors and crews.
Completed project ahead of schedule and under budget with zero safety incidents.
Site Superintendent
1 Year 10 Months
TIMEC CONSTRUCTORS | 04.2002 - 02.2004
Beyond Petroleum (BP), Carson
Site Project Manager managing capitol projects and shut- downs on civil, structure and piping.
Responsible for bids, estimates, and cost control.
Ultramar Diamond Shamrock
Project Manager for a new construction project of $12M Coker Hydro bins unit, managing construction supervisions.
Completed ahead of schedule and under budget.
Complete adherence to Ultramar’s safety policies and procedures resulting in zero safety incidents.
Project Manager
3 Years 3 Months
UMA CONSTRUCTORS | 01.1999 - 04.2002
Chevron Refinery, El Segundo, CA
Project Manager on the CO2 Plant for BOC, managing construction supervision for installation of 4,000 lf of 24” stainless steel piping and tie-in to existing systems.
Erected structural steel, installed Fin Fans, pumps and tanks.
GAF Materials Corporation, Shafter, CA
Project Manager responsible for a fiberglass mat machine installation plant.
Project Superintendent
1 Year 8 Months
BRINDERSON CONSTRUCTION | 05.1997 - 01.1999
Overall responsible for the construction from start to finish for multi-million-dollar project with a heavy focus on the mechanical aspect while also managing multiple sub-contractors
Project Superintendent
11 Years 7 Months
Fluor Daniel | 10.1985 - 05.1997
Responsible for all aspects for the project within the field including multiple crews, subcontracts, shutdowns, and all safety.
Principal Owner | Senior Principal Technical Program Manager at SelMil Project Management ConsultingPrincipal Owner | Senior Principal Technical Program Manager at SelMil Project Management Consulting