Dedicated Structure Superintendent with extensive experience in NCDOT/SCDOT bridge construction and project management. Committed to driving success through resourceful management, cost efficiency, and unwavering dedication to safety and quality.

Overview

19
19
years of professional experience

Work History

Structure Superintendent

Zachry Construction Corp.
04.2018 - Current
  • Oversaw NCDOT/SCDOT bridge construction projects from inception to completion, ensuring all phases, including demolition, substructure construction, and final deck pouring, adhered to the highest standards
  • Coordinated the use of specialized machinery, including the Bidwell machine and concrete pumps
  • Supervised multiple foremen and structures crews, emphasizing efficient resource management and safety
  • Managed budgets meticulously, consistently finding avenues for reducing operational costs
  • Employed effective scheduling techniques, optimizing the collaboration of crews, subcontractors, and vendors
  • Ensured compliance with erosion control and traffic control management protocols.
  • Reviewed plans and inspected ongoing construction to keep work in line with project goals.
  • Established successful procedures for day-to-day operations and long-term planning.
  • Managed complete construction process to maximize quality, cost-controls and efficiency.
  • Maintained safety onsite and upheld all OSHA regulations.
  • Monitored budgets and expenditures to maintain fiscal responsibility.
  • Trained workers in proper methods, equipment operation and safety procedures.
  • Oversaw daily operations at site, keeping team production moving at optimal pace.
  • Directed projects according to schedule and quality demands.
  • Prepared and submitted reports on job progress and safety conditions to upper management.

Rig Foreman

Chaparral Energy
07.2010 - 04.2018
  • Responsible for managing multiple rigs, contractors, equipment, and tools in repair of existing wells and completion of new wells.

Carpenter

JH Strain & Sons
01.2006 - 01.2010
  • Build and set forms, tie rebar, pour concrete in construction of bridge.

Carpenter

Granite construction co
01.2005 - 01.2006
  • Build and set forms, tie rebar, pour concrete in construction of bridges, walls, and footings.

Education

Riverside High School
Durham, NC

West texas A&m
Canyon, TX

Skills

  • Bridge Construction Expertise: Proficient in NCDOT/SCDOT bridge construction, bridge demolition, and substructure bridge construction
  • Technical Skills: Adept at bridge-related tasks ranging from excavation, drilled piers, pile driving, to construction of bridge foundations, caps, walls, and pouring bridge decks
  • Machinery & Logistics: Proficient in setting up the Bidwell machine, concrete pumps, and orchestrating logistics for bridge deck pours Expertise in temporary shoring planning for girder setting
  • Team Management: Proven experience supervising multiple foremen and crews, especially in construction of concrete culverts and culvert extensions
  • Resource Management: Demonstrated ability to manage and utilize resources efficiently and effectively, including budget management and operations cost reduction
  • Scheduling & Coordination: Strong scheduling skills, ensuring cohesive management of crews, equipment, subcontractors, and vendors to meet planned objectives
  • Certifications: Certified in erosion control management and traffic control management
  • Operational Skills: Skilled in managing structures submittals, RFI processes, and providing effective solutions

References

  • Mohammed Molad, Branch Civil, 919-633-8837
  • Chavis Lunceford, Flatiron, 713-474-6030

Personal Information

Title: Structure Superintendent

PROJECTS

  • I-40 Airport Blvd. Interchange: $45M, NCDOT Bid Build, Morrisville, NC
  • I-20 Bridge Replacement over Wateree River: $40M, SCDOT Bid Build, Columbia, SC
  • I-85 Mebane Oaks. Interchange: $15M, NCDOT Bid Build, Mebane, NC
  • Alston Avenue (NC 55) Widening Project: 60M, NCDOT Bid Build, Durham, NC
  • I-20 Highway Improvement and Widening: $101M, SCDOT Design-Build, Lexington, SC
  • I-40/I-77 Interchange Improvement: $90M, NCDOT Bid Build, Statesville, NC

Languages

English
Native or Bilingual
Spanish
Native or Bilingual

Timeline

Structure Superintendent

Zachry Construction Corp.
04.2018 - Current

Rig Foreman

Chaparral Energy
07.2010 - 04.2018

Carpenter

JH Strain & Sons
01.2006 - 01.2010

Carpenter

Granite construction co
01.2005 - 01.2006

Riverside High School

West texas A&m