Summary
Overview
Work History
Education
Skills
Timeline
Generic

Daniel Parker

Clarksville,United States

Summary

Seasoned Superintendent with a proven track record at JE Dunn Construction, adept in construction management and relationship building. Successfully led high-profile projects like the Hyatt Caption, demonstrating exceptional project coordination and on-site safety, culminating in significant profit margins and zero safety recordables. Achieved early project completions, underscoring a commitment to quality assurance, efficiency and safety.

Overview

13
13
years of professional experience

Work History

Superintendent

JE Dunn Construction
09.2023 - Current

Hyatt Caption- 78M

15 story hotel with 4 levels of underground parking in downtown Nashville's "Gulch" .

This was a great project, where i got my first shot at running a concrete structure package. I was in charge of daily activities, 6 week look ahead pull planning, OAC meetings, and inputting RFI's. This project challenged me in many ways but by the end of our project we made over profit than our buisness model had planned also, finishing structure on schedule with ZERO safety recordables.


American Cancer Society "Hope Lodge"-8M

Project specs- 60 guest room renovation levels 2-5

The entire first floor and reception area was remodeled.

This was my first stand alone superintendent project where i was the only one on site every day. I am very pleased with how this project ran and was complete 1 month ahead of schedule as well as making 8% profit where our forecast was 4%!! Also, this was yet another great project with ZERO safety recordables.


LG Chem- 1B

This is my current project where I am in charge of the interior office buildout, outbuildings ,as well as outbuilding civil connections. This project is by far the largest site i have ever been on, currently having 800-1k poeple on site every single day.


Superintendent

TRC CSI
09.2016 - 09.2023

Cordell Hull State Capital Parking Garage- This was my first project as a superintendent. We successfully completed this project with little to no lay down area and actually built a 5 story parking garage vertically in half and then came back and built to the new structure that we had completed. this project also contained boring 300 yards underneath the state capital and connecting to existing corridors. the structure itself is 5 stories with 3.5 stories underground and is 100% concealed with pre cast panels from street level. This project was about 25% complete when i stepped on the site and i was there until completion. total time on jobsite- 1 year


Airport Logistics Park- This project really taught me a lot as we were a turn key gc for 14 warehouses. ranging anywhere from 50k sq. ft. to 950k sq. ft. each of these warehouses had between 2-8 different tenant spaces in them. i was in charge of everything from schedules, verifying in field coordination of plans and trade partners. from footings to turning keys over to tenants and everything in between.

I was on this project from day 1- 100% complete.

total time on project-6 years.



Laborer/Lead Carpenter/ Carpenter Foreman

Brasfield & Gorrie
04.2012 - 09.2016

Station 40 Apartment Complex

Originally hired as a laborer, I quickly was promoted into the role of carpenter and by the end of the project I was our lead carpenter.

  • Loaded, unloaded, and moved material to and from storage and production areas.
  • Improved worksite efficiency by maintaining clean and organized work areas.


Bridgestone Tower

I got to this project as construction was still in the structure phase. I jumped into the concrete team and quickly found myself taking on more and more resposibility. eventually, I took over as carpenter foreman and was in charge of forming columns the day after concrete slab pours, forming, bracing, climbing and pouring concrete columns became my life's work for the next year until topping out the 36 floor high rise. After structure was complete i got to stay with the team and start running interior MEP trades.

Education

Communications

Jacksonville State University
Jacksonville, AL

Skills

  • Relationship building and management
  • Project coordination
  • Quality assurance
  • Construction management
  • Relationship building
  • On site safety

Timeline

Superintendent

JE Dunn Construction
09.2023 - Current

Superintendent

TRC CSI
09.2016 - 09.2023

Laborer/Lead Carpenter/ Carpenter Foreman

Brasfield & Gorrie
04.2012 - 09.2016

Communications

Jacksonville State University
Daniel Parker