Project controls and scheduling professional with nearly 3 years of experience supporting large, complex capital programs, including a $1B pharma project. Strong Primavera P6 expertise across schedule development, updates, critical path/constraint analysis, lookaheads, and change impact support. Collaborates closely with planning and execution teams to convert field progress into reliable forecasts, maintain schedule integrity, and enable timely project decisions.
Overview
4
4
years of professional experience
Work History
Scheduler
Linesight
Philadelphia, Pennsylvania
06.2025 - Current
Support planning and controls for a $1B pharma capital project, coordinating schedule updates across engineering, procurement, construction, and commissioning.
Work alongside the Senior Planner to develop and maintain Primavera P6 schedules (WBS, activity coding, calendars, logic ties, milestones) aligned with client governance.
Act as a bridge between planning and execution by translating field progress and constraints into P6 updates, and translating schedule priorities into actionable lookaheads for execution teams.
Perform critical path / near-critical path and constraint reviews, summarize key schedule drivers, and support development of mitigation options.
Maintain baseline and periodic updates. Prepare variance explanations and schedule narratives for stakeholder reviews and decision-making.
Support change impact reviews by quantifying schedule effects of scope changes, sequencing updates, and delayed deliverables, document assumptions and dependencies.
Conduct schedule quality checks in P6 (logic integrity, open ends, missing predecessors/successors, lag usage, coding consistency) to keep schedules review-ready.
Prepare 2–6 week lookaheadsand readiness tracking to align interdependent handoffs and reduce downstream delays.
Scheduling Analyst
Worldwide Professional Solutions
Ocotillo, USA
10.2023 - 05.2025
Developed and maintained baseline schedules, performed critical path analysis, and monitored float impacts
Experienced knowledge in float and possible impact on the Critical path.
Utilized Primavera P6 and advanced Excel to prepare, baseline, status, maintain (Add, Update, Modify, Delete), and report data to project schedules and project managers.
Created effective work breakdown structures, Gantt charts, activity networks, and relationship lines.
Automated reporting processes with VBA and created Power BI dashboards for stakeholder updates.
Supported project recovery decisions through data-driven analysis and forecast adjustments.
Coordinated 6-week lookaheads and ensured alignment with factory deadlines and deliverables.
Created a detailed Advanced Excel report on man-hours for the project with reference to each trade (Projected vs Actual) to track the trade's efficiency. This made a huge positive impact on the client, and requested continuous support throughout the project.
Applied Earned Value Management (EVM) principles to monitor project health and identify variances early.
Led initiatives to streamline scheduling processes, reducing manual effort by 20% through automation.
Monitored and reported schedule deliverables regularly to the client with desired data constraints.
Conducted meetings and data analysis reports to aid stakeholders in making key decisions of project recovery.